Walpole 400kV Substation

NESO connection site, host NGET.

Contracted here3.02 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date1 Aug 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue3,024.1 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Walpole 1 (Tertiary)31 May 20241 Aug 202557 MW
Walpole 2 (tertiary)31 May 202431 Oct 2027100 MW
Walpole31 May 202430 Oct 20307.1 MW
Norfolk00131 May 202430 Nov 2031860 MW
Walpole Flexible Generation31 May 202430 Jun 20332,000 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2025: 57 MW2027: 157 MW2030: 164 MW2031: 1.0 GW2033: 3.0 GW202520272029203120333.0 GW
0 MW2.0 GW4.0 GW2025: 57 MW2027: 157 MW2030: 164 MW2031: 1.0 GW2033: 3.0 GW20252028203120333.0 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202557 MW
2027157 MW
2030164.1 MW
20311,024.1 MW
20333,024.1 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Walpole 1 (Tertiary)57 MW0 MW1 Aug 2025not statedgate not printedScoping
2Walpole 2 (tertiary)100 MW57 MW31 Oct 2027not statedgate not printedConsents Approved
3Walpole7.1 MW157 MW30 Oct 2030not statedgate not printedScoping
4Norfolk001860 MW164.1 MW30 Nov 2031not statedgate not printedScoping
5Walpole Flexible Generation2,000 MW1,024.1 MW30 Jun 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025157 MW
20271100 MW
203017.1 MW
20311860 MW
203312,000 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Walpole Flexible GenerationHybrid2,000 MW30 Jun 2033Scoping
Norfolk001Hybrid860 MW30 Nov 2031Scoping
Sutton BridgeGas850 MWnot statedBuilt
Kings Lynn AGas395 MWnot statedBuilt
PeterboroughGas245 MWnot statedBuilt
Walpole 2 (tertiary)Hybrid100 MW31 Oct 2027Consents Approved
Walpole 1 (Tertiary)Hybrid57 MW1 Aug 2025Scoping
Walpole (PIVOTED POWER LLP)Hybrid57 MW30 Oct 2030Scoping
Peak Gen BEGAGas20.5 MWnot statedBuilt
Walpole Grid Services FacilityReactive compensation0 MW13 Jul 2026Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.