The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Lightsource Grendon PV+BESS
31 May 2024 to 31 Oct 2034 (gate not printed) - NatPower Kinoulton Green Energy Park
20 Dec 2024 to 31 Oct 2034 (gate 1) - Noventum - Astwood
27 Sep 2024 to 31 Oct 2034 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Lightsource Grendon PV+BESS | 31 May 2024 | 31 Oct 2034 | 240 MW |
| NatPower Kinoulton Green Energy Park | 20 Dec 2024 | 31 Oct 2034 | 1,330 MW |
| Noventum - Astwood | 27 Sep 2024 | 31 Oct 2034 | 480 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2034 | 2,050 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Lightsource Grendon PV+BESS | 240 MW | 0 MW | 31 Oct 2034 | not stated | gate not printed | Scoping |
| 2 | NatPower Kinoulton Green Energy Park | 1,330 MW | 240 MW | 31 Oct 2034 | 1 | gate 1 | Scoping |
| 3 | Noventum - Astwood | 480 MW | 1,570 MW | 31 Oct 2034 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2034 | 3 | 2,050 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| NatPower Kinoulton Green Energy Park | Battery storage | 1,330 MW | 31 Oct 2034 | Scoping |
| Noventum - Astwood | Hybrid | 480 MW | 31 Oct 2034 | Scoping |
| Lightsource Grendon PV+BESS | Hybrid | 240 MW | 31 Oct 2034 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.