West Burton 400kV Substation

NESO connection site, host NGET.

Contracted here1.20 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Jun 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,200 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
West Burton31 May 202430 Jun 2027120 MW
West Burton Solar Project31 May 202431 Oct 2028480 MW
Steeple Solar Farm31 May 202431 Oct 2029600 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2027: 120 MW2028: 600 MW2029: 1.2 GW2027202820291.2 GW
0 MW1.0 GW2.0 GW2027: 120 MW2028: 600 MW2029: 1.2 GW2027202820291.2 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027120 MW
2028600 MW
20291,200 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1West Burton120 MW0 MW30 Jun 20272gate 2Under Construction/Commissioning
2West Burton Solar Project480 MW120 MW31 Oct 20282gate 2Consents Approved
3Steeple Solar Farm600 MW600 MW31 Oct 2029not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20271120 MW
20281480 MW
20291600 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
West Burton BHybrid1,881 MW30 Oct 2034Built
Steeple Solar FarmHybrid600 MW31 Oct 2029Scoping
West Burton Solar ProjectHybrid480 MW31 Oct 2028Consents Approved
West Burton (ENSO GREEN HOLDINGS A LIMITED)Hybrid120 MW30 Jun 2027Under Construction/Commissioning

Supported by National Energy SO Open Data