The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- West Burton
31 May 2024 to 30 Jun 2027 (gate 2) - West Burton Solar Project
31 May 2024 to 31 Oct 2028 (gate 2) - Steeple Solar Farm
31 May 2024 to 31 Oct 2029 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| West Burton | 31 May 2024 | 30 Jun 2027 | 120 MW |
| West Burton Solar Project | 31 May 2024 | 31 Oct 2028 | 480 MW |
| Steeple Solar Farm | 31 May 2024 | 31 Oct 2029 | 600 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 120 MW |
| 2028 | 600 MW |
| 2029 | 1,200 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | West Burton | 120 MW | 0 MW | 30 Jun 2027 | 2 | gate 2 | Under Construction/Commissioning |
| 2 | West Burton Solar Project | 480 MW | 120 MW | 31 Oct 2028 | 2 | gate 2 | Consents Approved |
| 3 | Steeple Solar Farm | 600 MW | 600 MW | 31 Oct 2029 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 120 MW |
| 2028 | 1 | 480 MW |
| 2029 | 1 | 600 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| West Burton B | Hybrid | 1,881 MW | 30 Oct 2034 | Built |
| Steeple Solar Farm | Hybrid | 600 MW | 31 Oct 2029 | Scoping |
| West Burton Solar Project | Hybrid | 480 MW | 31 Oct 2028 | Consents Approved |
| West Burton (ENSO GREEN HOLDINGS A LIMITED) | Hybrid | 120 MW | 30 Jun 2027 | Under Construction/Commissioning |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.