West Weybridge 275kV Substation

NESO connection site, host NGET.

Contracted here0.11 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue114 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
West Weybridge31 May 202430 Sep 202857 MW
West Weybridge (Tertiary)31 May 202431 Oct 202549.9 MW
West Weybridge (Tertiary)31 May 202431 Oct 20277.1 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2025: 50 MW2027: 57 MW2028: 114 MW2025202620272028114 MW
0 MW100 MW200 MW2025: 50 MW2027: 57 MW2028: 114 MW2025202620272028114 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202549.9 MW
202757 MW
2028114 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1West Weybridge57 MW0 MW30 Sep 20282gate 2Consents Approved
2West Weybridge (Tertiary)49.9 MW57 MW31 Oct 2025not statedgate not printedScoping
3West Weybridge (Tertiary)7.1 MW106.9 MW31 Oct 2027not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025149.9 MW
202717.1 MW
2028157 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
West Weybridge (Tertiary)Hybrid57 MW31 Oct 2027Scoping
West Weybridge (EL (WEST WEYBRIDGE) LIMITED)Battery storage57 MW30 Sep 2028Consents Approved
West Weybridge (PIVOTED POWER LLP)Battery storage0 MW31 Oct 2027Scoping

Supported by National Energy SO Open Data