The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Strathruddie Farm Solar & Storage
7 Nov 2025 to 25 Apr 2025, date already passed (gate not printed) - Westfield PV Park
7 Nov 2025 to 1 Dec 2025, date already passed (gate not printed) - Westfield GSP
7 Nov 2025 to 31 Oct 2026 (gate not printed) - Fife 2 BESS
31 May 2024 to 14 Jun 2028 (gate not printed) - Fife Battery Storage
31 May 2024 to 30 Oct 2031 (gate not printed) - Lochore BESS
31 May 2024 to 31 Oct 2031 (gate 1) - Kirklands Farm BESS
31 May 2024 to 31 Oct 2031 (gate 1) - Westfield BESS
31 May 2024 to 31 Oct 2031 (gate 1) - Brunt Hill Wind Farm
22 Jul 2025 to 31 Oct 2031 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Strathruddie Farm Solar & Storage | 7 Nov 2025 | 25 Apr 2025 | 20 MW |
| Westfield PV Park | 7 Nov 2025 | 1 Dec 2025 | 29.9 MW |
| Westfield GSP | 7 Nov 2025 | 31 Oct 2026 | 20 MW |
| Fife 2 BESS | 31 May 2024 | 14 Jun 2028 | 49.9 MW |
| Fife Battery Storage | 31 May 2024 | 30 Oct 2031 | 200 MW |
| Lochore BESS | 31 May 2024 | 31 Oct 2031 | 900 MW |
| Kirklands Farm BESS | 31 May 2024 | 31 Oct 2031 | 200 MW |
| Westfield BESS | 31 May 2024 | 31 Oct 2031 | 350 MW |
| Brunt Hill Wind Farm | 22 Jul 2025 | 31 Oct 2031 | 99 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2025 | 49.9 MW |
| 2026 | 69.9 MW |
| 2028 | 119.8 MW |
| 2031 | 1,868.8 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Strathruddie Farm Solar & Storage | 20 MW | 0 MW | 25 Apr 2025 | not stated | gate not printed | Scoping |
| 2 | Westfield PV Park | 29.9 MW | 20 MW | 1 Dec 2025 | not stated | gate not printed | Consents Approved |
| 3 | Westfield GSP | 20 MW | 49.9 MW | 31 Oct 2026 | not stated | gate not printed | Scoping |
| 4 | Fife 2 BESS | 49.9 MW | 69.9 MW | 14 Jun 2028 | not stated | gate not printed | Scoping |
| 5 | Fife Battery Storage | 200 MW | 119.8 MW | 30 Oct 2031 | not stated | gate not printed | Scoping |
| 6 | Lochore BESS | 900 MW | 319.8 MW | 31 Oct 2031 | 1 | gate 1 | Scoping |
| 7 | Kirklands Farm BESS | 200 MW | 1,219.8 MW | 31 Oct 2031 | 1 | gate 1 | Scoping |
| 8 | Westfield BESS | 350 MW | 1,419.8 MW | 31 Oct 2031 | 1 | gate 1 | Scoping |
| 9 | Brunt Hill Wind Farm | 99 MW | 1,769.8 MW | 31 Oct 2031 | not stated | gate not printed | Awaiting Consents |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2025 | 2 | 49.9 MW |
| 2026 | 1 | 20 MW |
| 2028 | 1 | 49.9 MW |
| 2031 | 5 | 1,749 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Lochore BESS | Battery storage | 900 MW | 31 Oct 2031 | Scoping |
| Westfield BESS | Battery storage | 350 MW | 31 Oct 2031 | Scoping |
| Fife Battery Storage | Battery storage | 200 MW | 30 Oct 2031 | Scoping |
| Kirklands Farm BESS | Battery storage | 200 MW | 31 Oct 2031 | Scoping |
| Brunt Hill Wind Farm | Hybrid | 99 MW | 31 Oct 2031 | Awaiting Consents |
| Fife 2 BESS | Battery storage | 49.9 MW | 14 Jun 2028 | Scoping |
| Westfield PV Park | Solar | 29.9 MW | 1 Dec 2025 | Consents Approved |
| Westfield ERF | Battery storage | 25.1 MW | not stated | Built |
| Westfield GSP (SP DISTRIBUTION PLC) | Hybrid | 20 MW | 31 Oct 2026 | Scoping |
| Strathruddie Farm Solar & Storage | Hybrid | 20 MW | 25 Apr 2025 | Scoping |
| Westfield Wind Farm | Onshore wind | 12.5 MW | not stated | Built |
| Mossmorran Wind Farm | Onshore wind | 4.6 MW | not stated | Built |
Supported by National Energy SO Open Data