N84 Grid

Whitson 275kV Substation

NESO connection site, host NGET.

Contracted here0.48 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue484.9 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Whitson31 May 202431 Oct 202749.9 MW
Llanwern Phase 131 May 20241 Oct 202895 MW
Llanwern Phase 231 May 20241 Oct 2028190 MW
Whitson BESS31 May 202430 Oct 2037150 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW250 MW500 MW2027: 50 MW2028: 335 MW2037: 485 MW202720292031203320352037485 MW
0 MW250 MW500 MW2027: 50 MW2028: 335 MW2037: 485 MW2027203020332037485 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202749.9 MW
2028334.9 MW
2037484.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Whitson49.9 MW0 MW31 Oct 20271gate 1Scoping
2Llanwern Phase 195 MW49.9 MW1 Oct 2028not statedgate not printedAwaiting Consents
3Llanwern Phase 2190 MW144.9 MW1 Oct 2028not statedgate not printedAwaiting Consents
4Whitson BESS150 MW334.9 MW30 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027149.9 MW
20282285 MW
20371150 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Llanwern Phase 2Solar190 MW1 Oct 2028Awaiting Consents
Whitson BESSBattery storage150 MW30 Oct 2037Scoping
Llanwern Phase 1Hybrid95 MW1 Oct 2028Awaiting Consents
Whitson (PIVOTED POWER LLP)Battery storage49.9 MW31 Oct 2027Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.