The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Willington
31 May 2024 to 30 Jun 2026, date already passed (gate 1) - Willington East 1 (Tertiary)
31 May 2024 to 30 Oct 2027 (gate 1) - Willington East 2 (Tertiary)
31 May 2024 to 30 Jul 2028 (gate 1) - Willington PV & BESS
31 May 2024 to 31 Oct 2033 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Willington | 31 May 2024 | 30 Jun 2026 | 57 MW |
| Willington East 1 (Tertiary) | 31 May 2024 | 30 Oct 2027 | 47.5 MW |
| Willington East 2 (Tertiary) | 31 May 2024 | 30 Jul 2028 | 47.5 MW |
| Willington PV & BESS | 31 May 2024 | 31 Oct 2033 | 249.9 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 57 MW |
| 2027 | 104.5 MW |
| 2028 | 152 MW |
| 2033 | 401.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Willington | 57 MW | 0 MW | 30 Jun 2026 | 1 | gate 1 | Scoping |
| 2 | Willington East 1 (Tertiary) | 47.5 MW | 57 MW | 30 Oct 2027 | 1 | gate 1 | Scoping |
| 3 | Willington East 2 (Tertiary) | 47.5 MW | 104.5 MW | 30 Jul 2028 | 1 | gate 1 | Scoping |
| 4 | Willington PV & BESS | 249.9 MW | 152 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 57 MW |
| 2027 | 1 | 47.5 MW |
| 2028 | 1 | 47.5 MW |
| 2033 | 1 | 249.9 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Willington PV & BESS | Hybrid | 249.9 MW | 31 Oct 2033 | Scoping |
| Willington | Battery storage | 57 MW | 30 Jun 2026 | Scoping |
| Willington East 1 (Tertiary) | Hybrid | 47.5 MW | 30 Oct 2027 | Scoping |
| Willington East 2 (Tertiary) | Hybrid | 47.5 MW | 30 Jul 2028 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.