The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Abham Sgp (hybrid)
3 Nov 2022 to 1 Feb 2027 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Abham Sgp (hybrid) | 3 Nov 2022 | 1 Feb 2027 | 150 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 150 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Abham Sgp (hybrid) | 150 MW | 0 MW | 1 Feb 2027 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 150 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Abham Sgp (hybrid, 100 MW) | Hybrid | 100 MW | 1 Feb 2027 | Accepted to Connect |
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.