Alverdiscott Sgp

DNO substation.

Contracted here0.49 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date9 Nov 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue485.4 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Alverdiscott Sgp (solar)28 Oct 20219 Nov 2026100.8 MW
Alverdiscott Sgp (bess)20 Apr 202222 Dec 202625 MW
Alverdiscott Sgp (solar)1 Jun 202123 Mar 202760 MW
Alverdiscott Sgp (bess)14 Mar 20241 Jul 202799.8 MW
Alverdiscott Sgp (hybrid)17 Nov 20238 Nov 202799.8 MW
Alverdiscott Sgp (wind off)9 Nov 202131 Oct 2028100 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW250 MW500 MW2026: 126 MW2027: 385 MW2028: 485 MW202620272028485 MW
0 MW250 MW500 MW2026: 126 MW2027: 385 MW2028: 485 MW202620272028485 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026125.8 MW
2027385.4 MW
2028485.4 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Alverdiscott Sgp (solar)100.8 MW0 MW9 Nov 2026not statedgate not printedAccepted to Connect
2Alverdiscott Sgp (bess)25 MW100.8 MW22 Dec 2026not statedgate not printedAccepted to Connect
3Alverdiscott Sgp (solar)60 MW125.8 MW23 Mar 2027not statedgate not printedAccepted to Connect
4Alverdiscott Sgp (bess)99.8 MW185.8 MW1 Jul 2027not statedgate not printedAccepted to Connect
5Alverdiscott Sgp (hybrid)99.8 MW285.6 MW8 Nov 2027not statedgate not printedAccepted to Connect
6Alverdiscott Sgp (wind off)100 MW385.4 MW31 Oct 2028not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20262125.8 MW
20273259.6 MW
20281100 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Alverdiscott Sgp (offshore wind, 99.9 MW)Offshore wind99.9 MW31 Oct 2028Accepted to Connect
Alverdiscott Sgp (battery, 99.8 MW)Battery storage99.8 MW1 Jul 2027Accepted to Connect
Alverdiscott Sgp (solar, 49.9 MW)Solar49.9 MW9 Nov 2026Accepted to Connect
Alverdiscott Sgp (hybrid, 49.9 MW)Hybrid49.9 MW8 Nov 2027Accepted to Connect
Alverdiscott Sgp (solar, 47.5 MW)Solar47.5 MWnot statedConnected
Alverdiscott Sgp (solar, 40.28 MW)Solar40.28 MWnot statedConnected
Alverdiscott Sgp (solar, 31.16 MW)Solar31.16 MWnot statedConnected
Alverdiscott Sgp (solar, 30 MW)Solar30 MW23 Mar 2027Accepted to Connect
Alverdiscott Sgp (solar, 27.14 MW)Solar27.14 MWnot statedConnected
Alverdiscott Sgp (battery, 25 MW)Battery storage25 MW22 Dec 2026Accepted to Connect
Alverdiscott Sgp (hybrid, 13.35 MW)Hybrid13.35 MWnot statedConnected
Alverdiscott Sgp (onshore wind, 8.74 MW)Onshore wind8.74 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.