N84 Grid

Berkswell 132Kv S Stn

DNO substation.

Contracted here0.66 GWNot yet connected, as printed
Entries in the queue9entries with a printed MW
Earliest connection date11 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue465.3 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Berkswell 132Kv S Stn (bess)7 Feb 202211 Dec 202649.9 MW
Berkswell 132Kv S Stn (bess)19 May 202231 Dec 202640 MW
Berkswell 132Kv S Stn (solar)21 Jul 20203 Feb 202740 MW
Berkswell 132Kv S Stn (hybrid)6 Sep 20239 Mar 2027135.5 MW
Berkswell 132Kv S Stn (solar)19 Oct 202111 May 2027150 MW
Berkswell 132Kv S Stn (bess)31 Aug 202114 Jun 202749.9 MW
Berkswell 132Kv S Stn (bess)21 Aug 202330 Jul 202739.9 MW
Berkswell 132Kv S Stn (solar)12 Mar 20219 Sep 202760.65 MW
Berkswell 132Kv S Stn (bess)14 Sep 202226 Aug 203399 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2026: 90 MW2027: 566 MW2033: 665 MW20262027202820292030203120322033665 MW
0 MW400 MW800 MW2026: 90 MW2027: 566 MW2033: 665 MW2026202820302033665 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202689.9 MW
2027565.85 MW
2033664.85 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Berkswell 132Kv S Stn (bess)49.9 MW0 MW11 Dec 2026not statedgate not printedAccepted to Connect
2Berkswell 132Kv S Stn (bess)40 MW49.9 MW31 Dec 2026not statedgate not printedAccepted to Connect
3Berkswell 132Kv S Stn (solar)40 MW89.9 MW3 Feb 2027not statedgate not printedAccepted to Connect
4Berkswell 132Kv S Stn (hybrid)135.5 MW129.9 MW9 Mar 2027not statedgate not printedAccepted to Connect
5Berkswell 132Kv S Stn (solar)150 MW265.4 MW11 May 2027not statedgate not printedAccepted to Connect
6Berkswell 132Kv S Stn (bess)49.9 MW415.4 MW14 Jun 2027not statedgate not printedAccepted to Connect
7Berkswell 132Kv S Stn (bess)39.9 MW465.3 MW30 Jul 2027not statedgate not printedAccepted to Connect
8Berkswell 132Kv S Stn (solar)60.65 MW505.2 MW9 Sep 2027not statedgate not printedAccepted to Connect
9Berkswell 132Kv S Stn (bess)99 MW565.85 MW26 Aug 2033not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026289.9 MW
20276475.95 MW
2033199 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Berkswell 132Kv S Stn (battery, 99 MW)Battery storage99 MW26 Aug 2033Accepted to Connect
Berkswell 132Kv S Stn (solar, 75 MW)Solar75 MW11 May 2027Accepted to Connect
Berkswell 132Kv S Stn (battery, 49.9 MW)Battery storage49.9 MW11 Dec 2026Accepted to Connect
Berkswell 132Kv S Stn (battery, 49.9 MW)Battery storage49.9 MW30 Jul 2027Accepted to Connect
Berkswell 132Kv S Stn (battery, 49.9 MW)Battery storage49.9 MW14 Jun 2027Accepted to Connect
Berkswell 132Kv S Stn (hybrid, 45 MW)Hybrid45 MW9 Mar 2027Accepted to Connect
Berkswell 132Kv S Stn (solar, 40.65 MW)Solar40.65 MW9 Sep 2027Accepted to Connect
Berkswell 132Kv S Stn (battery, 40 MW)Battery storage40 MW31 Dec 2026Accepted to Connect
Berkswell 132Kv S Stn (solar, 40 MW)Solar40 MW3 Feb 2027Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.