The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Bicker Fen 132Kv S Stn (bess)
8 Nov 2021 to 15 Dec 2026 (gate not printed) - Bicker Fen 132Kv S Stn (bess)
4 Jun 2024 to 12 Feb 2027 (gate not printed) - Bicker Fen 132Kv S Stn (hybrid)
9 May 2022 to 19 Feb 2027 (gate not printed) - Bicker Fen 132Kv S Stn (solar)
11 Jul 2022 to 9 Mar 2027 (gate not printed) - Bicker Fen 132Kv S Stn (hybrid)
27 Jul 2023 to 9 Mar 2027 (gate not printed) - Bicker Fen 132Kv S Stn (hybrid)
24 Sep 2024 to 22 Mar 2027 (gate not printed) - Bicker Fen 132Kv S Stn (hybrid)
6 Oct 2025 to 6 Apr 2027 (gate not printed) - Bicker Fen 132Kv S Stn (bess)
31 May 2024 to 8 Apr 2027 (gate not printed) - Bicker Fen 132Kv S Stn (hybrid)
2 Dec 2022 to 1 Jul 2027 (gate not printed) - Bicker Fen 132Kv S Stn (bess)
15 Feb 2024 to 13 Aug 2027 (gate not printed) - Bicker Fen 132Kv S Stn (bess)
7 May 2024 to 7 Sep 2027 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Bicker Fen 132Kv S Stn (bess) | 8 Nov 2021 | 15 Dec 2026 | 248 MW |
| Bicker Fen 132Kv S Stn (bess) | 4 Jun 2024 | 12 Feb 2027 | 160 MW |
| Bicker Fen 132Kv S Stn (hybrid) | 9 May 2022 | 19 Feb 2027 | 480 MW |
| Bicker Fen 132Kv S Stn (solar) | 11 Jul 2022 | 9 Mar 2027 | 40 MW |
| Bicker Fen 132Kv S Stn (hybrid) | 27 Jul 2023 | 9 Mar 2027 | 60 MW |
| Bicker Fen 132Kv S Stn (hybrid) | 24 Sep 2024 | 22 Mar 2027 | 199.8 MW |
| Bicker Fen 132Kv S Stn (hybrid) | 6 Oct 2025 | 6 Apr 2027 | 299.7 MW |
| Bicker Fen 132Kv S Stn (bess) | 31 May 2024 | 8 Apr 2027 | 99.9 MW |
| Bicker Fen 132Kv S Stn (hybrid) | 2 Dec 2022 | 1 Jul 2027 | 70 MW |
| Bicker Fen 132Kv S Stn (bess) | 15 Feb 2024 | 13 Aug 2027 | 99.8 MW |
| Bicker Fen 132Kv S Stn (bess) | 7 May 2024 | 7 Sep 2027 | 99 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 248 MW |
| 2027 | 1,856.2 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Bicker Fen 132Kv S Stn (bess) | 248 MW | 0 MW | 15 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | Bicker Fen 132Kv S Stn (bess) | 160 MW | 248 MW | 12 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 3 | Bicker Fen 132Kv S Stn (hybrid) | 480 MW | 408 MW | 19 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 4 | Bicker Fen 132Kv S Stn (solar) | 40 MW | 888 MW | 9 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | Bicker Fen 132Kv S Stn (hybrid) | 60 MW | 928 MW | 9 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 6 | Bicker Fen 132Kv S Stn (hybrid) | 199.8 MW | 988 MW | 22 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 7 | Bicker Fen 132Kv S Stn (hybrid) | 299.7 MW | 1,187.8 MW | 6 Apr 2027 | not stated | gate not printed | Accepted to Connect |
| 8 | Bicker Fen 132Kv S Stn (bess) | 99.9 MW | 1,487.5 MW | 8 Apr 2027 | not stated | gate not printed | Accepted to Connect |
| 9 | Bicker Fen 132Kv S Stn (hybrid) | 70 MW | 1,587.4 MW | 1 Jul 2027 | not stated | gate not printed | Accepted to Connect |
| 10 | Bicker Fen 132Kv S Stn (bess) | 99.8 MW | 1,657.4 MW | 13 Aug 2027 | not stated | gate not printed | Accepted to Connect |
| 11 | Bicker Fen 132Kv S Stn (bess) | 99 MW | 1,757.2 MW | 7 Sep 2027 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 248 MW |
| 2027 | 10 | 1,608.2 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Bicker Fen 132Kv S Stn (battery, 248 MW) | Battery storage | 248 MW | 15 Dec 2026 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (hybrid, 240 MW) | Hybrid | 240 MW | 19 Feb 2027 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (battery, 160 MW) | Battery storage | 160 MW | 12 Feb 2027 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (hybrid, 99.9 MW) | Hybrid | 99.9 MW | 22 Mar 2027 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (battery, 99.9 MW) | Battery storage | 99.9 MW | 8 Apr 2027 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (hybrid, 99.9 MW) | Hybrid | 99.9 MW | 6 Apr 2027 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (battery, 99.8 MW) | Battery storage | 99.8 MW | 13 Aug 2027 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (battery, 99 MW) | Battery storage | 99 MW | 7 Sep 2027 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (solar, 48.38 MW) | Solar | 48.38 MW | not stated | Connected |
| Bicker Fen 132Kv S Stn (solar, 40 MW) | Solar | 40 MW | 9 Mar 2027 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (hybrid, 35 MW) | Hybrid | 35 MW | 1 Jul 2027 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (hybrid, 30 MW) | Hybrid | 30 MW | 9 Mar 2027 | Accepted to Connect |
| Bicker Fen 132Kv S Stn (solar) | Solar | 0 MW | not stated | Connected |