Bishops Wood 132Kv S Stn

DNO substation.

Contracted here0.63 GWNot yet connected, as printed
Entries in the queue17entries with a printed MW
Earliest connection date30 Aug 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue193.4 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Bishops Wood 132Kv S Stn (bess)15 Mar 202230 Aug 202635 MW
Bishops Wood 132Kv S Stn (bess)7 Jul 202118 Dec 202629.7 MW
Bishops Wood 132Kv S Stn (solar)1 Jun 202622 Dec 202636 MW
Bishops Wood 132Kv S Stn (bess)22 Sep 202231 Dec 202622.8 MW
Bishops Wood 132Kv S Stn (solar)6 Feb 20235 Jan 202720 MW
Bishops Wood 132Kv S Stn (bess)21 Feb 202414 Jan 202749.9 MW
Bishops Wood 132Kv S Stn (solar)16 Oct 202514 Jan 20275.3 MW
Bishops Wood 132Kv S Stn (solar)4 Feb 202621 Jan 20279.9 MW
Bishops Wood 132Kv S Stn (solar)7 Dec 202022 Jan 202740 MW
Bishops Wood 132Kv S Stn (bess)23 May 201728 Jan 202740 MW
Bishops Wood 132Kv S Stn (bess)23 May 202529 Jan 202750 MW
Bishops Wood 132Kv S Stn (solar)7 Apr 20214 Feb 202749.9 MW
Bishops Wood 132Kv S Stn (bess)5 Nov 202111 Feb 202740 MW
Bishops Wood 132Kv S Stn (solar)20 Mar 202611 Feb 202730 MW
Bishops Wood 132Kv S Stn (solar)17 Aug 202216 Feb 202720 MW
Bishops Wood 132Kv S Stn (bess)28 Nov 202414 Mar 2028130 MW
Bishops Wood 132Kv S Stn (solar)19 May 20251 Apr 203420 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2026: 124 MW2027: 479 MW2028: 609 MW2034: 629 MW20262028203020322034629 MW
0 MW400 MW800 MW2026: 124 MW2027: 479 MW2028: 609 MW2034: 629 MW2026202920322034629 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026123.5 MW
2027478.5 MW
2028608.5 MW
2034628.5 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Bishops Wood 132Kv S Stn (bess)35 MW0 MW30 Aug 2026not statedgate not printedAccepted to Connect
2Bishops Wood 132Kv S Stn (bess)29.7 MW35 MW18 Dec 2026not statedgate not printedAccepted to Connect
3Bishops Wood 132Kv S Stn (solar)36 MW64.7 MW22 Dec 2026not statedgate not printedAccepted to Connect
4Bishops Wood 132Kv S Stn (bess)22.8 MW100.7 MW31 Dec 2026not statedgate not printedAccepted to Connect
5Bishops Wood 132Kv S Stn (solar)20 MW123.5 MW5 Jan 2027not statedgate not printedAccepted to Connect
6Bishops Wood 132Kv S Stn (bess)49.9 MW143.5 MW14 Jan 2027not statedgate not printedAccepted to Connect
7Bishops Wood 132Kv S Stn (solar)5.3 MW193.4 MW14 Jan 2027not statedgate not printedAccepted to Connect
8Bishops Wood 132Kv S Stn (solar)9.9 MW198.7 MW21 Jan 2027not statedgate not printedAccepted to Connect
9Bishops Wood 132Kv S Stn (solar)40 MW208.6 MW22 Jan 2027not statedgate not printedAccepted to Connect
10Bishops Wood 132Kv S Stn (bess)40 MW248.6 MW28 Jan 2027not statedgate not printedAccepted to Connect
11Bishops Wood 132Kv S Stn (bess)50 MW288.6 MW29 Jan 2027not statedgate not printedAccepted to Connect
12Bishops Wood 132Kv S Stn (solar)49.9 MW338.6 MW4 Feb 2027not statedgate not printedAccepted to Connect
13Bishops Wood 132Kv S Stn (bess)40 MW388.5 MW11 Feb 2027not statedgate not printedAccepted to Connect
14Bishops Wood 132Kv S Stn (solar)30 MW428.5 MW11 Feb 2027not statedgate not printedAccepted to Connect
15Bishops Wood 132Kv S Stn (solar)20 MW458.5 MW16 Feb 2027not statedgate not printedAccepted to Connect
16Bishops Wood 132Kv S Stn (bess)130 MW478.5 MW14 Mar 2028not statedgate not printedAccepted to Connect
17Bishops Wood 132Kv S Stn (solar)20 MW608.5 MW1 Apr 2034not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20264123.5 MW
202711355 MW
20281130 MW
2034120 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Bishops Wood 132Kv S Stn (battery, 130 MW)Battery storage130 MW14 Mar 2028Accepted to Connect
Bishops Wood 132Kv S Stn (battery, 50 MW)Battery storage50 MW29 Jan 2027Accepted to Connect
Bishops Wood 132Kv S Stn (solar, 49.9 MW)Solar49.9 MW4 Feb 2027Accepted to Connect
Bishops Wood 132Kv S Stn (battery, 49.9 MW)Battery storage49.9 MW14 Jan 2027Accepted to Connect
Bishops Wood 132Kv S Stn (solar, 47.41 MW)Solar47.41 MWnot statedConnected
Bishops Wood 132Kv S Stn (solar, 40 MW)Solar40 MW22 Jan 2027Accepted to Connect
Bishops Wood 132Kv S Stn (battery, 40 MW)Battery storage40 MW11 Feb 2027Accepted to Connect
Bishops Wood 132Kv S Stn (battery, 40 MW)Battery storage40 MW28 Jan 2027Accepted to Connect
Bishops Wood 132Kv S Stn (solar, 36 MW)Solar36 MW22 Dec 2026Accepted to Connect
Bishops Wood 132Kv S Stn (battery, 35 MW)Battery storage35 MW30 Aug 2026Accepted to Connect
Bishops Wood 132Kv S Stn (solar, 30 MW)Solar30 MW11 Feb 2027Accepted to Connect
Bishops Wood 132Kv S Stn (battery, 29.7 MW)Battery storage29.7 MW18 Dec 2026Accepted to Connect
Bishops Wood 132Kv S Stn (battery, 22.8 MW)Battery storage22.8 MW31 Dec 2026Accepted to Connect
Bishops Wood 132Kv S Stn (solar, 20 MW)Solar20 MW1 Apr 2034Accepted to Connect
Bishops Wood 132Kv S Stn (solar, 20 MW)Solar20 MW16 Feb 2027Accepted to Connect
Bishops Wood 132Kv S Stn (solar, 9.9 MW)Solar9.9 MW21 Jan 2027Accepted to Connect
Bishops Wood 132Kv S Stn (solar, 5.3 MW)Solar5.3 MW14 Jan 2027Accepted to Connect
Bishops Wood 132Kv S Stn (solar)Solar0 MW5 Jan 2027Accepted to Connect

Supported by NGED Open Data