N84 Grid

Bridgwater Sgp

DNO substation.

Contracted here0.19 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date11 Feb 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue189.8 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Bridgwater Sgp (solar)24 Nov 202311 Feb 202749.9 MW
Bridgwater Sgp (bess)8 Sep 20219 Sep 202949.9 MW
Bridgwater Sgp (bess)13 Sep 20221 Jan 203790 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 50 MW2029: 100 MW2037: 190 MW202720292031203320352037190 MW
0 MW100 MW200 MW2027: 50 MW2029: 100 MW2037: 190 MW2027203020332037190 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202749.9 MW
202999.8 MW
2037189.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Bridgwater Sgp (solar)49.9 MW0 MW11 Feb 2027not statedgate not printedAccepted to Connect
2Bridgwater Sgp (bess)49.9 MW49.9 MW9 Sep 2029not statedgate not printedAccepted to Connect
3Bridgwater Sgp (bess)90 MW99.8 MW1 Jan 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027149.9 MW
2029149.9 MW
2037190 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Bridgwater Sgp (battery, 90 MW)Battery storage90 MW1 Jan 2037Accepted to Connect
Bridgwater Sgp (solar, 49.9 MW)Solar49.9 MW11 Feb 2027Accepted to Connect
Bridgwater Sgp (battery, 49.9 MW)Battery storage49.9 MW9 Sep 2029Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.