The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Bushbury D 132Kv (solar)
14 Dec 2021 to 13 Oct 2026, date already passed (gate not printed) - Bushbury D 132Kv (bess)
13 Sep 2021 to 7 Jan 2027 (gate not printed) - Bushbury D 132Kv (bess)
9 Jan 2023 to 8 Jan 2027 (gate not printed) - Bushbury D 132Kv (bess)
25 Jan 2022 to 27 Jan 2027 (gate not printed) - Bushbury D 132Kv (solar)
16 Jan 2020 to 2 Feb 2027 (gate not printed) - Bushbury D 132Kv (solar)
13 Sep 2021 to 2 Feb 2027 (gate not printed) - Bushbury D 132Kv (solar)
27 Aug 2020 to 4 Feb 2027 (gate not printed) - Bushbury D 132Kv (solar)
8 Mar 2022 to 4 Feb 2027 (gate not printed) - Bushbury D 132Kv (bess)
27 Jul 2022 to 12 Feb 2027 (gate not printed) - Bushbury D 132Kv (solar)
27 Mar 2026 to 25 Feb 2027 (gate not printed) - Bushbury D 132Kv (solar)
26 Apr 2022 to 1 Apr 2028 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Bushbury D 132Kv (solar) | 14 Dec 2021 | 13 Oct 2026 | 39.59 MW |
| Bushbury D 132Kv (bess) | 13 Sep 2021 | 7 Jan 2027 | 49.9 MW |
| Bushbury D 132Kv (bess) | 9 Jan 2023 | 8 Jan 2027 | 49.9 MW |
| Bushbury D 132Kv (bess) | 25 Jan 2022 | 27 Jan 2027 | 7 MW |
| Bushbury D 132Kv (solar) | 16 Jan 2020 | 2 Feb 2027 | 40 MW |
| Bushbury D 132Kv (solar) | 13 Sep 2021 | 2 Feb 2027 | 40 MW |
| Bushbury D 132Kv (solar) | 27 Aug 2020 | 4 Feb 2027 | 49.9 MW |
| Bushbury D 132Kv (solar) | 8 Mar 2022 | 4 Feb 2027 | 30 MW |
| Bushbury D 132Kv (bess) | 27 Jul 2022 | 12 Feb 2027 | 70.4 MW |
| Bushbury D 132Kv (solar) | 27 Mar 2026 | 25 Feb 2027 | 0.44 MW |
| Bushbury D 132Kv (solar) | 26 Apr 2022 | 1 Apr 2028 | 18 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 39.59 MW |
| 2027 | 377.13 MW |
| 2028 | 395.13 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Bushbury D 132Kv (solar) | 39.59 MW | 0 MW | 13 Oct 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | Bushbury D 132Kv (bess) | 49.9 MW | 39.59 MW | 7 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 3 | Bushbury D 132Kv (bess) | 49.9 MW | 89.49 MW | 8 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 4 | Bushbury D 132Kv (bess) | 7 MW | 139.39 MW | 27 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | Bushbury D 132Kv (solar) | 40 MW | 146.39 MW | 2 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 6 | Bushbury D 132Kv (solar) | 40 MW | 186.39 MW | 2 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 7 | Bushbury D 132Kv (solar) | 49.9 MW | 226.39 MW | 4 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 8 | Bushbury D 132Kv (solar) | 30 MW | 276.29 MW | 4 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 9 | Bushbury D 132Kv (bess) | 70.4 MW | 306.29 MW | 12 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 10 | Bushbury D 132Kv (solar) | 0.44 MW | 376.69 MW | 25 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 11 | Bushbury D 132Kv (solar) | 18 MW | 377.13 MW | 1 Apr 2028 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 39.59 MW |
| 2027 | 9 | 337.54 MW |
| 2028 | 1 | 18 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Bushbury D 132Kv (battery, 70.4 MW) | Battery storage | 70.4 MW | 12 Feb 2027 | Accepted to Connect |
| Bushbury D 132Kv (battery, 49.9 MW) | Battery storage | 49.9 MW | 8 Jan 2027 | Accepted to Connect |
| Bushbury D 132Kv (solar, 49.9 MW) | Solar | 49.9 MW | 4 Feb 2027 | Accepted to Connect |
| Bushbury D 132Kv (battery, 49.9 MW) | Battery storage | 49.9 MW | 7 Jan 2027 | Accepted to Connect |
| Bushbury D 132Kv (solar, 40 MW) | Solar | 40 MW | 2 Feb 2027 | Accepted to Connect |
| Bushbury D 132Kv (solar, 40 MW) | Solar | 40 MW | 2 Feb 2027 | Accepted to Connect |
| Bushbury D 132Kv (solar, 39.59 MW) | Solar | 39.59 MW | 13 Oct 2026 | Accepted to Connect |
| Bushbury D 132Kv (solar, 30 MW) | Solar | 30 MW | 4 Feb 2027 | Accepted to Connect |
| Bushbury D 132Kv (solar, 18 MW) | Solar | 18 MW | 1 Apr 2028 | Accepted to Connect |
| Bushbury D 132Kv (battery, 7 MW) | Battery storage | 7 MW | 27 Jan 2027 | Accepted to Connect |
| Bushbury D 132Kv (solar, 0.44 MW) | Solar | 0.44 MW | 25 Feb 2027 | Accepted to Connect |