N84 Grid

Cauldon

DNO substation.

Contracted here0.01 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date5 Sep 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue8.18 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Cauldon (solar)13 Jan 2026 to 5 Sep 2026, date already passed (gate not printed)
  • Cauldon (solar)10 Jul 2026 to 21 Oct 2026, date already passed (gate not printed)
  • Cauldon (solar)21 Jul 2026 to 29 Oct 2026 (gate not printed)
  • Cauldon (solar)14 Apr 2025 to 19 Jan 2027 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Cauldon (solar)13 Jan 20265 Sep 20260.06 MW
Cauldon (solar)10 Jul 202621 Oct 20260.06 MW
Cauldon (solar)21 Jul 202629 Oct 20260.06 MW
Cauldon (solar)14 Apr 202519 Jan 20278 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW5 MW10 MW2026: 0 MW2027: 8 MW202620278 MW
0 MW5 MW10 MW2026: 0 MW2027: 8 MW202620278 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20260.18 MW
20278.18 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Cauldon (solar)0.06 MW0 MW5 Sep 2026not statedgate not printedAccepted to Connect
2Cauldon (solar)0.06 MW0.06 MW21 Oct 2026not statedgate not printedAccepted to Connect
3Cauldon (solar)0.06 MW0.12 MW29 Oct 2026not statedgate not printedAccepted to Connect
4Cauldon (solar)8 MW0.18 MW19 Jan 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202630.18 MW
202718 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Cauldon (onshore wind, 0.1 MW)Onshore wind0.1 MWnot statedConnected
Cauldon (onshore wind, 0.09 MW)Onshore wind0.09 MWnot statedConnected
Cauldon (onshore wind, 0.09 MW)Onshore wind0.09 MWnot statedConnected
Cauldon (onshore wind, 0.09 MW)Onshore wind0.09 MWnot statedConnected
Cauldon (solar, 0.06 MW)Solar0.06 MW21 Oct 2026Accepted to Connect
Cauldon (solar, 0.06 MW)Solar0.06 MWnot statedConnected
Cauldon (solar, 0.06 MW)Solar0.06 MW29 Oct 2026Accepted to Connect
Cauldon (solar, 0.06 MW)Solar0.06 MW5 Sep 2026Accepted to Connect
Cauldon (onshore wind, 0.05 MW)Onshore wind0.05 MWnot statedConnected
Cauldon (solar)Solar0 MW19 Jan 2027Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.