DNO substation.

Contracted here0.81 GWNot yet connected, as printed
Entries in the queue12entries with a printed MW
Earliest connection date16 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue204.66 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Cellarhead 132Kv (bess)23 Sep 202116 Dec 202613 MW
Cellarhead 132Kv (other)19 Nov 202118 Dec 202610 MW
Cellarhead 132Kv (wind on)27 Oct 202322 Dec 202654 MW
Cellarhead 132Kv (solar)16 Jul 202430 Dec 202615 MW
Cellarhead 132Kv (bess)20 Jan 202514 Jan 202799.9 MW
Cellarhead 132Kv (solar)9 Nov 202325 Jan 202712.76 MW
Cellarhead 132Kv (bess)22 Sep 202127 Jan 202749.35 MW
Cellarhead 132Kv (solar)17 Aug 20219 Feb 202740 MW
Cellarhead 132Kv (bess)7 May 202110 Feb 2027280 MW
Cellarhead 132Kv (bess)2 Aug 20221 Sep 202840 MW
Cellarhead 132Kv (bess)18 Oct 202419 Feb 202999 MW
Cellarhead 132Kv (bess)31 Aug 20211 Oct 203399.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2026: 92 MW2027: 574 MW2028: 614 MW2029: 713 MW2033: 813 MW20262027202820292030203120322033813 MW
0 MW500 MW1.0 GW2026: 92 MW2027: 574 MW2028: 614 MW2029: 713 MW2033: 813 MW2026202820302033813 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202692 MW
2027574.01 MW
2028614.01 MW
2029713.01 MW
2033812.91 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Cellarhead 132Kv (bess)13 MW0 MW16 Dec 2026not statedgate not printedAccepted to Connect
2Cellarhead 132Kv (other)10 MW13 MW18 Dec 2026not statedgate not printedAccepted to Connect
3Cellarhead 132Kv (wind on)54 MW23 MW22 Dec 2026not statedgate not printedAccepted to Connect
4Cellarhead 132Kv (solar)15 MW77 MW30 Dec 2026not statedgate not printedAccepted to Connect
5Cellarhead 132Kv (bess)99.9 MW92 MW14 Jan 2027not statedgate not printedAccepted to Connect
6Cellarhead 132Kv (solar)12.76 MW191.9 MW25 Jan 2027not statedgate not printedAccepted to Connect
7Cellarhead 132Kv (bess)49.35 MW204.66 MW27 Jan 2027not statedgate not printedAccepted to Connect
8Cellarhead 132Kv (solar)40 MW254.01 MW9 Feb 2027not statedgate not printedAccepted to Connect
9Cellarhead 132Kv (bess)280 MW294.01 MW10 Feb 2027not statedgate not printedAccepted to Connect
10Cellarhead 132Kv (bess)40 MW574.01 MW1 Sep 2028not statedgate not printedAccepted to Connect
11Cellarhead 132Kv (bess)99 MW614.01 MW19 Feb 2029not statedgate not printedAccepted to Connect
12Cellarhead 132Kv (bess)99.9 MW713.01 MW1 Oct 2033not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026492 MW
20275482.01 MW
2028140 MW
2029199 MW
2033199.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Cellarhead 132Kv (battery, 280 MW)Battery storage280 MW10 Feb 2027Accepted to Connect
Cellarhead 132Kv (battery, 99.9 MW)Battery storage99.9 MW1 Oct 2033Accepted to Connect
Cellarhead 132Kv (battery, 99.9 MW)Battery storage99.9 MW14 Jan 2027Accepted to Connect
Cellarhead 132Kv (battery, 99 MW)Battery storage99 MW19 Feb 2029Accepted to Connect
Cellarhead 132Kv (onshore wind, 54 MW)Onshore wind54 MW22 Dec 2026Accepted to Connect
Cellarhead 132Kv (battery, 49.35 MW)Battery storage49.35 MW27 Jan 2027Accepted to Connect
Cellarhead 132Kv (battery, 40 MW)Battery storage40 MW1 Sep 2028Accepted to Connect
Cellarhead 132Kv (solar, 40 MW)Solar40 MW9 Feb 2027Accepted to Connect
Cellarhead 132Kv (solar, 15 MW)Solar15 MW30 Dec 2026Accepted to Connect
Cellarhead 132Kv (battery, 13 MW)Battery storage13 MW16 Dec 2026Accepted to Connect
Cellarhead 132Kv (solar, 12.76 MW)Solar12.76 MW25 Jan 2027Accepted to Connect
Cellarhead 132Kv (other, 10 MW)Other10 MW18 Dec 2026Accepted to Connect