The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Cellarhead 132Kv (bess)
23 Sep 2021 to 16 Dec 2026 (gate not printed) - Cellarhead 132Kv (other)
19 Nov 2021 to 18 Dec 2026 (gate not printed) - Cellarhead 132Kv (wind on)
27 Oct 2023 to 22 Dec 2026 (gate not printed) - Cellarhead 132Kv (solar)
16 Jul 2024 to 30 Dec 2026 (gate not printed) - Cellarhead 132Kv (bess)
20 Jan 2025 to 14 Jan 2027 (gate not printed) - Cellarhead 132Kv (solar)
9 Nov 2023 to 25 Jan 2027 (gate not printed) - Cellarhead 132Kv (bess)
22 Sep 2021 to 27 Jan 2027 (gate not printed) - Cellarhead 132Kv (solar)
17 Aug 2021 to 9 Feb 2027 (gate not printed) - Cellarhead 132Kv (bess)
7 May 2021 to 10 Feb 2027 (gate not printed) - Cellarhead 132Kv (bess)
2 Aug 2022 to 1 Sep 2028 (gate not printed) - Cellarhead 132Kv (bess)
18 Oct 2024 to 19 Feb 2029 (gate not printed) - Cellarhead 132Kv (bess)
31 Aug 2021 to 1 Oct 2033 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Cellarhead 132Kv (bess) | 23 Sep 2021 | 16 Dec 2026 | 13 MW |
| Cellarhead 132Kv (other) | 19 Nov 2021 | 18 Dec 2026 | 10 MW |
| Cellarhead 132Kv (wind on) | 27 Oct 2023 | 22 Dec 2026 | 54 MW |
| Cellarhead 132Kv (solar) | 16 Jul 2024 | 30 Dec 2026 | 15 MW |
| Cellarhead 132Kv (bess) | 20 Jan 2025 | 14 Jan 2027 | 99.9 MW |
| Cellarhead 132Kv (solar) | 9 Nov 2023 | 25 Jan 2027 | 12.76 MW |
| Cellarhead 132Kv (bess) | 22 Sep 2021 | 27 Jan 2027 | 49.35 MW |
| Cellarhead 132Kv (solar) | 17 Aug 2021 | 9 Feb 2027 | 40 MW |
| Cellarhead 132Kv (bess) | 7 May 2021 | 10 Feb 2027 | 280 MW |
| Cellarhead 132Kv (bess) | 2 Aug 2022 | 1 Sep 2028 | 40 MW |
| Cellarhead 132Kv (bess) | 18 Oct 2024 | 19 Feb 2029 | 99 MW |
| Cellarhead 132Kv (bess) | 31 Aug 2021 | 1 Oct 2033 | 99.9 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 92 MW |
| 2027 | 574.01 MW |
| 2028 | 614.01 MW |
| 2029 | 713.01 MW |
| 2033 | 812.91 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Cellarhead 132Kv (bess) | 13 MW | 0 MW | 16 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | Cellarhead 132Kv (other) | 10 MW | 13 MW | 18 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 3 | Cellarhead 132Kv (wind on) | 54 MW | 23 MW | 22 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 4 | Cellarhead 132Kv (solar) | 15 MW | 77 MW | 30 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 5 | Cellarhead 132Kv (bess) | 99.9 MW | 92 MW | 14 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 6 | Cellarhead 132Kv (solar) | 12.76 MW | 191.9 MW | 25 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 7 | Cellarhead 132Kv (bess) | 49.35 MW | 204.66 MW | 27 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 8 | Cellarhead 132Kv (solar) | 40 MW | 254.01 MW | 9 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 9 | Cellarhead 132Kv (bess) | 280 MW | 294.01 MW | 10 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 10 | Cellarhead 132Kv (bess) | 40 MW | 574.01 MW | 1 Sep 2028 | not stated | gate not printed | Accepted to Connect |
| 11 | Cellarhead 132Kv (bess) | 99 MW | 614.01 MW | 19 Feb 2029 | not stated | gate not printed | Accepted to Connect |
| 12 | Cellarhead 132Kv (bess) | 99.9 MW | 713.01 MW | 1 Oct 2033 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 4 | 92 MW |
| 2027 | 5 | 482.01 MW |
| 2028 | 1 | 40 MW |
| 2029 | 1 | 99 MW |
| 2033 | 1 | 99.9 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Cellarhead 132Kv (battery, 280 MW) | Battery storage | 280 MW | 10 Feb 2027 | Accepted to Connect |
| Cellarhead 132Kv (battery, 99.9 MW) | Battery storage | 99.9 MW | 1 Oct 2033 | Accepted to Connect |
| Cellarhead 132Kv (battery, 99.9 MW) | Battery storage | 99.9 MW | 14 Jan 2027 | Accepted to Connect |
| Cellarhead 132Kv (battery, 99 MW) | Battery storage | 99 MW | 19 Feb 2029 | Accepted to Connect |
| Cellarhead 132Kv (onshore wind, 54 MW) | Onshore wind | 54 MW | 22 Dec 2026 | Accepted to Connect |
| Cellarhead 132Kv (battery, 49.35 MW) | Battery storage | 49.35 MW | 27 Jan 2027 | Accepted to Connect |
| Cellarhead 132Kv (battery, 40 MW) | Battery storage | 40 MW | 1 Sep 2028 | Accepted to Connect |
| Cellarhead 132Kv (solar, 40 MW) | Solar | 40 MW | 9 Feb 2027 | Accepted to Connect |
| Cellarhead 132Kv (solar, 15 MW) | Solar | 15 MW | 30 Dec 2026 | Accepted to Connect |
| Cellarhead 132Kv (battery, 13 MW) | Battery storage | 13 MW | 16 Dec 2026 | Accepted to Connect |
| Cellarhead 132Kv (solar, 12.76 MW) | Solar | 12.76 MW | 25 Jan 2027 | Accepted to Connect |
| Cellarhead 132Kv (other, 10 MW) | Other | 10 MW | 18 Dec 2026 | Accepted to Connect |