The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Chesterfield 132Kv S Stn (bess)
16 Aug 2024 to 2 Feb 2027 (gate not printed) - Chesterfield 132Kv S Stn (bess)
8 Nov 2021 to 22 Feb 2027 (gate not printed) - Chesterfield 132Kv S Stn (solar)
11 Sep 2020 to 28 Apr 2027 (gate not printed) - Chesterfield 132Kv S Stn (solar)
29 Jan 2021 to 1 Sep 2027 (gate not printed) - Chesterfield 132Kv S Stn (hybrid)
11 Mar 2024 to 21 Sep 2027 (gate not printed) - Chesterfield 132Kv S Stn (hybrid)
19 Apr 2024 to 5 Nov 2027 (gate not printed) - Chesterfield 132Kv S Stn (bess)
10 Jun 2024 to 5 Nov 2027 (gate not printed) - Chesterfield 132Kv S Stn (solar)
15 Nov 2024 to 2 Apr 2029 (gate not printed) - Chesterfield 33Kv S Stn (bess)
14 Dec 2023 to 1 Dec 2032 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Chesterfield 132Kv S Stn (bess) | 16 Aug 2024 | 2 Feb 2027 | 80.3 MW |
| Chesterfield 132Kv S Stn (bess) | 8 Nov 2021 | 22 Feb 2027 | 99.9 MW |
| Chesterfield 132Kv S Stn (solar) | 11 Sep 2020 | 28 Apr 2027 | 50 MW |
| Chesterfield 132Kv S Stn (solar) | 29 Jan 2021 | 1 Sep 2027 | 99.8 MW |
| Chesterfield 132Kv S Stn (hybrid) | 11 Mar 2024 | 21 Sep 2027 | 99 MW |
| Chesterfield 132Kv S Stn (hybrid) | 19 Apr 2024 | 5 Nov 2027 | 99 MW |
| Chesterfield 132Kv S Stn (bess) | 10 Jun 2024 | 5 Nov 2027 | 49.99 MW |
| Chesterfield 132Kv S Stn (solar) | 15 Nov 2024 | 2 Apr 2029 | 20 MW |
| Chesterfield 33Kv S Stn (bess) | 14 Dec 2023 | 1 Dec 2032 | 25 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 577.99 MW |
| 2029 | 597.99 MW |
| 2032 | 622.99 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Chesterfield 132Kv S Stn (bess) | 80.3 MW | 0 MW | 2 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 2 | Chesterfield 132Kv S Stn (bess) | 99.9 MW | 80.3 MW | 22 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 3 | Chesterfield 132Kv S Stn (solar) | 50 MW | 180.2 MW | 28 Apr 2027 | not stated | gate not printed | Accepted to Connect |
| 4 | Chesterfield 132Kv S Stn (solar) | 99.8 MW | 230.2 MW | 1 Sep 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | Chesterfield 132Kv S Stn (hybrid) | 99 MW | 330 MW | 21 Sep 2027 | not stated | gate not printed | Accepted to Connect |
| 6 | Chesterfield 132Kv S Stn (hybrid) | 99 MW | 429 MW | 5 Nov 2027 | not stated | gate not printed | Accepted to Connect |
| 7 | Chesterfield 132Kv S Stn (bess) | 49.99 MW | 528 MW | 5 Nov 2027 | not stated | gate not printed | Accepted to Connect |
| 8 | Chesterfield 132Kv S Stn (solar) | 20 MW | 577.99 MW | 2 Apr 2029 | not stated | gate not printed | Accepted to Connect |
| 9 | Chesterfield 33Kv S Stn (bess) | 25 MW | 597.99 MW | 1 Dec 2032 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 7 | 577.99 MW |
| 2029 | 1 | 20 MW |
| 2032 | 1 | 25 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Chesterfield 132Kv S Stn (battery, 99.9 MW) | Battery storage | 99.9 MW | 22 Feb 2027 | Accepted to Connect |
| Chesterfield 132Kv S Stn (battery, 80.3 MW) | Battery storage | 80.3 MW | 2 Feb 2027 | Accepted to Connect |
| Chesterfield 132Kv S Stn (solar, 50 MW) | Solar | 50 MW | 28 Apr 2027 | Accepted to Connect |
| Chesterfield 132Kv S Stn (battery, 49.99 MW) | Battery storage | 49.99 MW | 5 Nov 2027 | Accepted to Connect |
| Chesterfield 132Kv S Stn (solar, 49.9 MW) | Solar | 49.9 MW | 1 Sep 2027 | Accepted to Connect |
| Chesterfield 132Kv S Stn (hybrid, 49.5 MW) | Hybrid | 49.5 MW | 21 Sep 2027 | Accepted to Connect |
| Chesterfield 132Kv S Stn (hybrid, 49.5 MW) | Hybrid | 49.5 MW | 5 Nov 2027 | Accepted to Connect |
| Chesterfield 132Kv S Stn (solar, 47.41 MW) | Solar | 47.41 MW | not stated | Connected |
| Chesterfield 132Kv S Stn (solar, 38 MW) | Solar | 38 MW | not stated | Connected |
| Chesterfield 132Kv S Stn (battery, 25 MW) | Battery storage | 25 MW | 1 Dec 2032 | Accepted to Connect |
| Chesterfield 132Kv S Stn (solar, 20 MW) | Solar | 20 MW | 2 Apr 2029 | Accepted to Connect |
| Chesterfield 132Kv S Stn (battery, 19 MW) | Battery storage | 19 MW | not stated | Connected |
| Chesterfield 132Kv S Stn (solar, 5.7 MW) | Solar | 5.7 MW | not stated | Connected |
| Chesterfield 132Kv S Stn (solar, 4.28 MW) | Solar | 4.28 MW | not stated | Connected |
| Chesterfield 132Kv S Stn (solar, 3.56 MW) | Solar | 3.56 MW | not stated | Connected |