N84 Grid

Chesterfield 132Kv S Stn

DNO substation.

Contracted here0.62 GWNot yet connected, as printed
Entries in the queue9entries with a printed MW
Earliest connection date2 Feb 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue528 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Chesterfield 132Kv S Stn (bess)16 Aug 20242 Feb 202780.3 MW
Chesterfield 132Kv S Stn (bess)8 Nov 202122 Feb 202799.9 MW
Chesterfield 132Kv S Stn (solar)11 Sep 202028 Apr 202750 MW
Chesterfield 132Kv S Stn (solar)29 Jan 20211 Sep 202799.8 MW
Chesterfield 132Kv S Stn (hybrid)11 Mar 202421 Sep 202799 MW
Chesterfield 132Kv S Stn (hybrid)19 Apr 20245 Nov 202799 MW
Chesterfield 132Kv S Stn (bess)10 Jun 20245 Nov 202749.99 MW
Chesterfield 132Kv S Stn (solar)15 Nov 20242 Apr 202920 MW
Chesterfield 33Kv S Stn (bess)14 Dec 20231 Dec 203225 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2027: 578 MW2029: 598 MW2032: 623 MW202720282029203020312032623 MW
0 MW400 MW800 MW2027: 578 MW2029: 598 MW2032: 623 MW2027202920312032623 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027577.99 MW
2029597.99 MW
2032622.99 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Chesterfield 132Kv S Stn (bess)80.3 MW0 MW2 Feb 2027not statedgate not printedAccepted to Connect
2Chesterfield 132Kv S Stn (bess)99.9 MW80.3 MW22 Feb 2027not statedgate not printedAccepted to Connect
3Chesterfield 132Kv S Stn (solar)50 MW180.2 MW28 Apr 2027not statedgate not printedAccepted to Connect
4Chesterfield 132Kv S Stn (solar)99.8 MW230.2 MW1 Sep 2027not statedgate not printedAccepted to Connect
5Chesterfield 132Kv S Stn (hybrid)99 MW330 MW21 Sep 2027not statedgate not printedAccepted to Connect
6Chesterfield 132Kv S Stn (hybrid)99 MW429 MW5 Nov 2027not statedgate not printedAccepted to Connect
7Chesterfield 132Kv S Stn (bess)49.99 MW528 MW5 Nov 2027not statedgate not printedAccepted to Connect
8Chesterfield 132Kv S Stn (solar)20 MW577.99 MW2 Apr 2029not statedgate not printedAccepted to Connect
9Chesterfield 33Kv S Stn (bess)25 MW597.99 MW1 Dec 2032not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20277577.99 MW
2029120 MW
2032125 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Chesterfield 132Kv S Stn (battery, 99.9 MW)Battery storage99.9 MW22 Feb 2027Accepted to Connect
Chesterfield 132Kv S Stn (battery, 80.3 MW)Battery storage80.3 MW2 Feb 2027Accepted to Connect
Chesterfield 132Kv S Stn (solar, 50 MW)Solar50 MW28 Apr 2027Accepted to Connect
Chesterfield 132Kv S Stn (battery, 49.99 MW)Battery storage49.99 MW5 Nov 2027Accepted to Connect
Chesterfield 132Kv S Stn (solar, 49.9 MW)Solar49.9 MW1 Sep 2027Accepted to Connect
Chesterfield 132Kv S Stn (hybrid, 49.5 MW)Hybrid49.5 MW21 Sep 2027Accepted to Connect
Chesterfield 132Kv S Stn (hybrid, 49.5 MW)Hybrid49.5 MW5 Nov 2027Accepted to Connect
Chesterfield 132Kv S Stn (solar, 47.41 MW)Solar47.41 MWnot statedConnected
Chesterfield 132Kv S Stn (solar, 38 MW)Solar38 MWnot statedConnected
Chesterfield 132Kv S Stn (battery, 25 MW)Battery storage25 MW1 Dec 2032Accepted to Connect
Chesterfield 132Kv S Stn (solar, 20 MW)Solar20 MW2 Apr 2029Accepted to Connect
Chesterfield 132Kv S Stn (battery, 19 MW)Battery storage19 MWnot statedConnected
Chesterfield 132Kv S Stn (solar, 5.7 MW)Solar5.7 MWnot statedConnected
Chesterfield 132Kv S Stn (solar, 4.28 MW)Solar4.28 MWnot statedConnected
Chesterfield 132Kv S Stn (solar, 3.56 MW)Solar3.56 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.