N84 Grid

Churchill Bsp 132Kv

DNO substation.

Contracted here0.19 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date24 Mar 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue143.6 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Churchill Bsp 132Kv (solar)2 Mar 202024 Mar 202738 MW
Churchill Bsp 132Kv (solar)22 Mar 202124 Mar 202713.7 MW
Churchill Bsp 132Kv (hybrid)26 May 202312 Apr 202720 MW
Churchill Bsp 132Kv (bess)20 Jul 202315 Apr 202749.9 MW
Churchill Bsp 132Kv (solar)30 Aug 202222 Apr 202712 MW
Churchill Bsp 132Kv (solar)30 Aug 202222 Jun 202710 MW
Churchill Bsp 132Kv (other)20 Apr 202130 Jul 202749.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 194 MW2027194 MW
0 MW100 MW200 MW2027: 194 MW2027194 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027193.5 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Churchill Bsp 132Kv (solar)38 MW0 MW24 Mar 2027not statedgate not printedAccepted to Connect
2Churchill Bsp 132Kv (solar)13.7 MW38 MW24 Mar 2027not statedgate not printedAccepted to Connect
3Churchill Bsp 132Kv (hybrid)20 MW51.7 MW12 Apr 2027not statedgate not printedAccepted to Connect
4Churchill Bsp 132Kv (bess)49.9 MW71.7 MW15 Apr 2027not statedgate not printedAccepted to Connect
5Churchill Bsp 132Kv (solar)12 MW121.6 MW22 Apr 2027not statedgate not printedAccepted to Connect
6Churchill Bsp 132Kv (solar)10 MW133.6 MW22 Jun 2027not statedgate not printedAccepted to Connect
7Churchill Bsp 132Kv (other)49.9 MW143.6 MW30 Jul 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20277193.5 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Churchill Bsp 132Kv (other, 49.9 MW)Other49.9 MW30 Jul 2027Accepted to Connect
Churchill Bsp 132Kv (battery, 49.9 MW)Battery storage49.9 MW15 Apr 2027Accepted to Connect
Churchill Bsp 132Kv (solar, 38 MW)Solar38 MW24 Mar 2027Accepted to Connect
Churchill Bsp 132Kv (hybrid, 15 MW)Hybrid15 MW12 Apr 2027Accepted to Connect
Churchill Bsp 132Kv (solar, 14.54 MW)Solar14.54 MWnot statedConnected
Churchill Bsp 132Kv (solar, 13.7 MW)Solar13.7 MW24 Mar 2027Accepted to Connect
Churchill Bsp 132Kv (solar, 12 MW)Solar12 MW22 Apr 2027Accepted to Connect
Churchill Bsp 132Kv (solar, 10 MW)Solar10 MW22 Jun 2027Accepted to Connect
Churchill Bsp 132Kv (solar, 7.6 MW)Solar7.6 MWnot statedConnected
Churchill Bsp 132Kv (solar, 6.41 MW)Solar6.41 MWnot statedConnected
Churchill Bsp 132Kv (solar, 6.17 MW)Solar6.18 MWnot statedConnected
Churchill Bsp 132Kv (solar, 4.73 MW)Solar4.73 MWnot statedConnected
Churchill Bsp 132Kv (solar, 4.1 MW)Solar4.1 MWnot statedConnected