N84 Grid

Coventry 132Kv S Stn

DNO substation.

Contracted here1.08 GWNot yet connected, as printed
Entries in the queue15entries with a printed MW
Earliest connection date9 Nov 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue369.68 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Coventry 132Kv S Stn (hybrid)3 Jun 20259 Nov 202699.98 MW
Coventry 132Kv S Stn (bess)31 May 20233 Dec 202649.9 MW
Coventry 132Kv S Stn (bess)2 Jun 20237 Jan 202749.5 MW
Coventry 132Kv S Stn (solar)11 Oct 202116 Feb 202740.6 MW
Coventry 132Kv S Stn (hybrid)28 Jul 202316 Feb 202779.8 MW
Coventry 132Kv S Stn (bess)25 Apr 202415 Mar 202749.9 MW
Coventry 132Kv S Stn (bess)2 Sep 202116 Mar 202749.5 MW
Coventry 132Kv S Stn (bess)22 Jul 202214 Apr 2027200 MW
Coventry 132Kv S Stn (hybrid)14 Dec 202321 Apr 202720 MW
Coventry 132Kv S Stn (hybrid)26 Nov 202424 Jun 202759.9 MW
Coventry 132Kv S Stn (bess)16 Nov 202227 Jul 202799.9 MW
Coventry 132Kv S Stn (wind on)17 Mar 202613 Aug 202764.8 MW
Coventry 132Kv S Stn (hybrid)24 Mar 20257 Sep 202799 MW
Coventry 132Kv S Stn (solar)28 Feb 202330 Oct 203715 MW
Coventry 132Kv S Stn (bess)4 Sep 202430 Oct 2037100 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2026: 150 MW2027: 963 MW2037: 1.1 GW2026202820302032203420371.1 GW
0 MW1.0 GW2.0 GW2026: 150 MW2027: 963 MW2037: 1.1 GW202620292032203520371.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026149.88 MW
2027962.78 MW
20371,077.78 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Coventry 132Kv S Stn (hybrid)99.98 MW0 MW9 Nov 2026not statedgate not printedAccepted to Connect
2Coventry 132Kv S Stn (bess)49.9 MW99.98 MW3 Dec 2026not statedgate not printedAccepted to Connect
3Coventry 132Kv S Stn (bess)49.5 MW149.88 MW7 Jan 2027not statedgate not printedAccepted to Connect
4Coventry 132Kv S Stn (solar)40.6 MW199.38 MW16 Feb 2027not statedgate not printedAccepted to Connect
5Coventry 132Kv S Stn (hybrid)79.8 MW239.98 MW16 Feb 2027not statedgate not printedAccepted to Connect
6Coventry 132Kv S Stn (bess)49.9 MW319.78 MW15 Mar 2027not statedgate not printedAccepted to Connect
7Coventry 132Kv S Stn (bess)49.5 MW369.68 MW16 Mar 2027not statedgate not printedAccepted to Connect
8Coventry 132Kv S Stn (bess)200 MW419.18 MW14 Apr 2027not statedgate not printedAccepted to Connect
9Coventry 132Kv S Stn (hybrid)20 MW619.18 MW21 Apr 2027not statedgate not printedAccepted to Connect
10Coventry 132Kv S Stn (hybrid)59.9 MW639.18 MW24 Jun 2027not statedgate not printedAccepted to Connect
11Coventry 132Kv S Stn (bess)99.9 MW699.08 MW27 Jul 2027not statedgate not printedAccepted to Connect
12Coventry 132Kv S Stn (wind on)64.8 MW798.98 MW13 Aug 2027not statedgate not printedAccepted to Connect
13Coventry 132Kv S Stn (hybrid)99 MW863.78 MW7 Sep 2027not statedgate not printedAccepted to Connect
14Coventry 132Kv S Stn (solar)15 MW962.78 MW30 Oct 2037not statedgate not printedAccepted to Connect
15Coventry 132Kv S Stn (bess)100 MW977.78 MW30 Oct 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20262149.88 MW
202711812.9 MW
20372115 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Coventry 132Kv S Stn (battery, 200 MW)Battery storage200 MW14 Apr 2027Accepted to Connect
Coventry 132Kv S Stn (battery, 100 MW)Battery storage100 MW30 Oct 2037Accepted to Connect
Coventry 132Kv S Stn (battery, 99.9 MW)Battery storage99.9 MW27 Jul 2027Accepted to Connect
Coventry 132Kv S Stn (hybrid, 99 MW)Hybrid99 MW7 Sep 2027Accepted to Connect
Coventry 132Kv S Stn (onshore wind, 64.8 MW)Onshore wind64.8 MW13 Aug 2027Accepted to Connect
Coventry 132Kv S Stn (hybrid, 50 MW)Hybrid50 MW24 Jun 2027Accepted to Connect
Coventry 132Kv S Stn (hybrid, 49.99 MW)Hybrid49.99 MW9 Nov 2026Accepted to Connect
Coventry 132Kv S Stn (battery, 49.9 MW)Battery storage49.9 MW3 Dec 2026Accepted to Connect
Coventry 132Kv S Stn (battery, 49.5 MW)Battery storage49.5 MW16 Mar 2027Accepted to Connect
Coventry 132Kv S Stn (battery, 49.5 MW)Battery storage49.5 MW7 Jan 2027Accepted to Connect
Coventry 132Kv S Stn (solar, 47.41 MW)Solar47.41 MWnot statedConnected
Coventry 132Kv S Stn (solar, 40.6 MW)Solar40.6 MW16 Feb 2027Accepted to Connect
Coventry 132Kv S Stn (battery, 40 MW)Battery storage40 MW15 Mar 2027Accepted to Connect
Coventry 132Kv S Stn (hybrid, 39.9 MW)Hybrid39.9 MW16 Feb 2027Accepted to Connect
Coventry 132Kv S Stn (solar, 36.1 MW)Solar36.1 MWnot statedConnected
Coventry 132Kv S Stn (onshore wind, 20.9 MW)Onshore wind20.9 MWnot statedConnected
Coventry 132Kv S Stn (solar, 15 MW)Solar15 MW30 Oct 2037Accepted to Connect
Coventry 132Kv S Stn (hybrid, 10 MW)Hybrid10 MW21 Apr 2027Accepted to Connect
Coventry 132Kv S Stn (onshore wind, 7.79 MW)Onshore wind7.79 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.