N84 Grid

Dowlais Grid

DNO substation.

Contracted here0.04 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date22 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue44.4 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Dowlais Grid (bess)9 Jul 202122 Dec 202615 MW
Dowlais Grid (wind on)14 Apr 202230 Apr 202729.4 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW25 MW50 MW2026: 15 MW2027: 44 MW2026202744 MW
0 MW25 MW50 MW2026: 15 MW2027: 44 MW2026202744 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202615 MW
202744.4 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Dowlais Grid (bess)15 MW0 MW22 Dec 2026not statedgate not printedAccepted to Connect
2Dowlais Grid (wind on)29.4 MW15 MW30 Apr 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026115 MW
2027129.4 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Dowlais Grid (onshore wind, 29.4 MW)Onshore wind29.4 MW30 Apr 2027Accepted to Connect
Dowlais Grid (gas, 21.34 MW)Gas21.34 MWnot statedConnected
Dowlais Grid (battery, 15 MW)Battery storage15 MW22 Dec 2026Accepted to Connect
Dowlais Grid (solar, 9.5 MW)Solar9.5 MWnot statedConnected
Dowlais Grid (onshore wind, 6 MW)Onshore wind6 MWnot statedConnected
Dowlais Grid (solar, 3.88 MW)Solar3.88 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.