N84 Grid

Drakelow 132Kv

DNO substation.

Contracted here0.29 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date3 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue293.3 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Drakelow 132Kv (bess)15 Jan 20213 Dec 202690 MW
Drakelow 132Kv (bess)4 Aug 201615 Feb 202740 MW
Drakelow 132Kv (bess)9 Dec 20245 May 202735 MW
Drakelow 132Kv (bess)7 Feb 202313 Sep 202749.9 MW
Drakelow 132Kv (bess)8 Dec 202130 Sep 202778.4 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2026: 90 MW2027: 293 MW20262027293 MW
0 MW200 MW400 MW2026: 90 MW2027: 293 MW20262027293 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202690 MW
2027293.3 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Drakelow 132Kv (bess)90 MW0 MW3 Dec 2026not statedgate not printedAccepted to Connect
2Drakelow 132Kv (bess)40 MW90 MW15 Feb 2027not statedgate not printedAccepted to Connect
3Drakelow 132Kv (bess)35 MW130 MW5 May 2027not statedgate not printedAccepted to Connect
4Drakelow 132Kv (bess)49.9 MW165 MW13 Sep 2027not statedgate not printedAccepted to Connect
5Drakelow 132Kv (bess)78.4 MW214.9 MW30 Sep 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026190 MW
20274203.3 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Drakelow 132Kv (battery, 90 MW)Battery storage90 MW3 Dec 2026Accepted to Connect
Drakelow 132Kv (battery, 78.4 MW)Battery storage78.4 MW30 Sep 2027Accepted to Connect
Drakelow 132Kv (battery, 49.9 MW)Battery storage49.9 MW13 Sep 2027Accepted to Connect
Drakelow 132Kv (battery, 40 MW)Battery storage40 MW15 Feb 2027Accepted to Connect
Drakelow 132Kv (battery, 35 MW)Battery storage35 MW5 May 2027Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.