The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- East Aberthaw Primary (solar)
10 Jun 2024 to 28 Aug 2026, date already passed (gate not printed) - East Aberthaw Primary (solar)
13 Apr 2023 to 22 Oct 2026, date already passed (gate not printed) - East Aberthaw Primary (solar)
8 Jan 2026 to 10 Nov 2026 (gate not printed) - East Aberthaw (solar)
18 Dec 2019 to 26 Jan 2027 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| East Aberthaw Primary (solar) | 10 Jun 2024 | 28 Aug 2026 | 0.95 MW |
| East Aberthaw Primary (solar) | 13 Apr 2023 | 22 Oct 2026 | 4.89 MW |
| East Aberthaw Primary (solar) | 8 Jan 2026 | 10 Nov 2026 | 0.05 MW |
| East Aberthaw (solar) | 18 Dec 2019 | 26 Jan 2027 | 20 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 5.89 MW |
| 2027 | 25.89 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | East Aberthaw Primary (solar) | 0.95 MW | 0 MW | 28 Aug 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | East Aberthaw Primary (solar) | 4.89 MW | 0.95 MW | 22 Oct 2026 | not stated | gate not printed | Accepted to Connect |
| 3 | East Aberthaw Primary (solar) | 0.05 MW | 5.84 MW | 10 Nov 2026 | not stated | gate not printed | Accepted to Connect |
| 4 | East Aberthaw (solar) | 20 MW | 5.89 MW | 26 Jan 2027 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 3 | 5.89 MW |
| 2027 | 1 | 20 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| East Aberthaw (solar, 20 MW) | Solar | 20 MW | 26 Jan 2027 | Accepted to Connect |
| East Aberthaw (solar, 5.32 MW) | Solar | 5.32 MW | not stated | Connected |
| East Aberthaw (solar, 4.45 MW) | Solar | 4.45 MW | not stated | Connected |
| East Aberthaw (solar, 3.8 MW) | Solar | 3.8 MW | not stated | Connected |
| East Aberthaw (solar, 3.71 MW) | Solar | 3.71 MW | not stated | Connected |
| East Aberthaw (solar, 3.61 MW) | Solar | 3.61 MW | not stated | Connected |
| East Aberthaw (solar, 0.95 MW) | Solar | 0.95 MW | 28 Aug 2026 | Accepted to Connect |
| East Aberthaw (solar, 0.95 MW) | Solar | 0.95 MW | 22 Oct 2026 | Accepted to Connect |
| East Aberthaw (solar, 0.9 MW) | Solar | 0.9 MW | not stated | Connected |
| East Aberthaw (thermal, 0.47 MW) | Thermal | 0.48 MW | not stated | Connected |
| East Aberthaw (solar, 0.05 MW) | Solar | 0.05 MW | 10 Nov 2026 | Accepted to Connect |
Supported by NGED Open Data