N84 Grid

East Aberthaw

DNO substation.

Contracted here0.03 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date28 Aug 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue25.89 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
East Aberthaw Primary (solar)10 Jun 202428 Aug 20260.95 MW
East Aberthaw Primary (solar)13 Apr 202322 Oct 20264.89 MW
East Aberthaw Primary (solar)8 Jan 202610 Nov 20260.05 MW
East Aberthaw (solar)18 Dec 201926 Jan 202720 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW20 MW40 MW2026: 6 MW2027: 26 MW2026202726 MW
0 MW20 MW40 MW2026: 6 MW2027: 26 MW2026202726 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20265.89 MW
202725.89 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1East Aberthaw Primary (solar)0.95 MW0 MW28 Aug 2026not statedgate not printedAccepted to Connect
2East Aberthaw Primary (solar)4.89 MW0.95 MW22 Oct 2026not statedgate not printedAccepted to Connect
3East Aberthaw Primary (solar)0.05 MW5.84 MW10 Nov 2026not statedgate not printedAccepted to Connect
4East Aberthaw (solar)20 MW5.89 MW26 Jan 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202635.89 MW
2027120 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
East Aberthaw (solar, 20 MW)Solar20 MW26 Jan 2027Accepted to Connect
East Aberthaw (solar, 5.32 MW)Solar5.32 MWnot statedConnected
East Aberthaw (solar, 4.45 MW)Solar4.45 MWnot statedConnected
East Aberthaw (solar, 3.8 MW)Solar3.8 MWnot statedConnected
East Aberthaw (solar, 3.71 MW)Solar3.71 MWnot statedConnected
East Aberthaw (solar, 3.61 MW)Solar3.61 MWnot statedConnected
East Aberthaw (solar, 0.95 MW)Solar0.95 MW28 Aug 2026Accepted to Connect
East Aberthaw (solar, 0.95 MW)Solar0.95 MW22 Oct 2026Accepted to Connect
East Aberthaw (solar, 0.9 MW)Solar0.9 MWnot statedConnected
East Aberthaw (thermal, 0.47 MW)Thermal0.48 MWnot statedConnected
East Aberthaw (solar, 0.05 MW)Solar0.05 MW10 Nov 2026Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.