The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- East Claydon 132Kv S Stn (solar)
7 Dec 2020 to 22 Oct 2026, date already passed (gate not printed) - East Claydon 132Kv S Stn (solar)
12 Jan 2018 to 17 Nov 2026 (gate not printed) - East Claydon 132Kv S Stn (solar)
24 Jun 2024 to 7 Dec 2026 (gate not printed) - East Claydon 132Kv S Stn (solar)
20 Apr 2018 to 4 Jan 2027 (gate not printed) - East Claydon 132Kv S Stn (solar)
9 Dec 2020 to 16 Feb 2027 (gate not printed) - East Claydon 132Kv S Stn (bess)
11 Jun 2020 to 13 Apr 2027 (gate not printed) - East Claydon 132Kv S Stn (hybrid)
24 Dec 2024 to 30 Apr 2027 (gate not printed) - East Claydon 132Kv S Stn (solar)
9 Apr 2020 to 19 May 2027 (gate not printed) - East Claydon 132Kv S Stn (bess)
27 Jan 2025 to 1 Jun 2027 (gate not printed) - East Claydon 132Kv S Stn (solar)
14 Mar 2023 to 28 Jul 2027 (gate not printed) - East Claydon 132Kv S Stn (bess)
25 Mar 2024 to 29 Nov 2027 (gate not printed) - East Claydon 132Kv S Stn (hybrid)
20 Nov 2024 to 31 Oct 2037 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| East Claydon 132Kv S Stn (solar) | 7 Dec 2020 | 22 Oct 2026 | 129.87 MW |
| East Claydon 132Kv S Stn (solar) | 12 Jan 2018 | 17 Nov 2026 | 25 MW |
| East Claydon 132Kv S Stn (solar) | 24 Jun 2024 | 7 Dec 2026 | 49.99 MW |
| East Claydon 132Kv S Stn (solar) | 20 Apr 2018 | 4 Jan 2027 | 40 MW |
| East Claydon 132Kv S Stn (solar) | 9 Dec 2020 | 16 Feb 2027 | 40 MW |
| East Claydon 132Kv S Stn (bess) | 11 Jun 2020 | 13 Apr 2027 | 49.9 MW |
| East Claydon 132Kv S Stn (hybrid) | 24 Dec 2024 | 30 Apr 2027 | 50 MW |
| East Claydon 132Kv S Stn (solar) | 9 Apr 2020 | 19 May 2027 | 49.9 MW |
| East Claydon 132Kv S Stn (bess) | 27 Jan 2025 | 1 Jun 2027 | 99.9 MW |
| East Claydon 132Kv S Stn (solar) | 14 Mar 2023 | 28 Jul 2027 | 49.9 MW |
| East Claydon 132Kv S Stn (bess) | 25 Mar 2024 | 29 Nov 2027 | 49.9 MW |
| East Claydon 132Kv S Stn (hybrid) | 20 Nov 2024 | 31 Oct 2037 | 99.8 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 204.86 MW |
| 2027 | 634.36 MW |
| 2037 | 734.16 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | East Claydon 132Kv S Stn (solar) | 129.87 MW | 0 MW | 22 Oct 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | East Claydon 132Kv S Stn (solar) | 25 MW | 129.87 MW | 17 Nov 2026 | not stated | gate not printed | Accepted to Connect |
| 3 | East Claydon 132Kv S Stn (solar) | 49.99 MW | 154.87 MW | 7 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 4 | East Claydon 132Kv S Stn (solar) | 40 MW | 204.86 MW | 4 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | East Claydon 132Kv S Stn (solar) | 40 MW | 244.86 MW | 16 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 6 | East Claydon 132Kv S Stn (bess) | 49.9 MW | 284.86 MW | 13 Apr 2027 | not stated | gate not printed | Accepted to Connect |
| 7 | East Claydon 132Kv S Stn (hybrid) | 50 MW | 334.76 MW | 30 Apr 2027 | not stated | gate not printed | Accepted to Connect |
| 8 | East Claydon 132Kv S Stn (solar) | 49.9 MW | 384.76 MW | 19 May 2027 | not stated | gate not printed | Accepted to Connect |
| 9 | East Claydon 132Kv S Stn (bess) | 99.9 MW | 434.66 MW | 1 Jun 2027 | not stated | gate not printed | Accepted to Connect |
| 10 | East Claydon 132Kv S Stn (solar) | 49.9 MW | 534.56 MW | 28 Jul 2027 | not stated | gate not printed | Accepted to Connect |
| 11 | East Claydon 132Kv S Stn (bess) | 49.9 MW | 584.46 MW | 29 Nov 2027 | not stated | gate not printed | Accepted to Connect |
| 12 | East Claydon 132Kv S Stn (hybrid) | 99.8 MW | 634.36 MW | 31 Oct 2037 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 3 | 204.86 MW |
| 2027 | 8 | 429.5 MW |
| 2037 | 1 | 99.8 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| East Claydon 132Kv S Stn (solar, 129.87 MW) | Solar | 129.87 MW | 22 Oct 2026 | Accepted to Connect |
| East Claydon 132Kv S Stn (battery, 99.9 MW) | Battery storage | 99.9 MW | 1 Jun 2027 | Accepted to Connect |
| East Claydon 132Kv S Stn (solar, 49.99 MW) | Solar | 49.99 MW | 7 Dec 2026 | Accepted to Connect |
| East Claydon 132Kv S Stn (solar, 49.95 MW) | Solar | 49.95 MW | 28 Jul 2027 | Accepted to Connect |
| East Claydon 132Kv S Stn (hybrid, 49.9 MW) | Hybrid | 49.9 MW | 31 Oct 2037 | Accepted to Connect |
| East Claydon 132Kv S Stn (battery, 49.9 MW) | Battery storage | 49.9 MW | 13 Apr 2027 | Accepted to Connect |
| East Claydon 132Kv S Stn (battery, 49.9 MW) | Battery storage | 49.9 MW | 29 Nov 2027 | Accepted to Connect |
| East Claydon 132Kv S Stn (solar, 49.9 MW) | Solar | 49.9 MW | 19 May 2027 | Accepted to Connect |
| East Claydon 132Kv S Stn (solar, 40 MW) | Solar | 40 MW | 16 Feb 2027 | Accepted to Connect |
| East Claydon 132Kv S Stn (hybrid, 40 MW) | Hybrid | 40 MW | 30 Apr 2027 | Accepted to Connect |
| East Claydon 132Kv S Stn (solar, 40 MW) | Solar | 40 MW | 4 Jan 2027 | Accepted to Connect |
| East Claydon 132Kv S Stn (solar, 25 MW) | Solar | 25 MW | 17 Nov 2026 | Accepted to Connect |