N84 Grid

East Claydon 132Kv S Stn

DNO substation.

Contracted here0.73 GWNot yet connected, as printed
Entries in the queue12entries with a printed MW
Earliest connection date22 Oct 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue334.76 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
East Claydon 132Kv S Stn (solar)7 Dec 202022 Oct 2026129.87 MW
East Claydon 132Kv S Stn (solar)12 Jan 201817 Nov 202625 MW
East Claydon 132Kv S Stn (solar)24 Jun 20247 Dec 202649.99 MW
East Claydon 132Kv S Stn (solar)20 Apr 20184 Jan 202740 MW
East Claydon 132Kv S Stn (solar)9 Dec 202016 Feb 202740 MW
East Claydon 132Kv S Stn (bess)11 Jun 202013 Apr 202749.9 MW
East Claydon 132Kv S Stn (hybrid)24 Dec 202430 Apr 202750 MW
East Claydon 132Kv S Stn (solar)9 Apr 202019 May 202749.9 MW
East Claydon 132Kv S Stn (bess)27 Jan 20251 Jun 202799.9 MW
East Claydon 132Kv S Stn (solar)14 Mar 202328 Jul 202749.9 MW
East Claydon 132Kv S Stn (bess)25 Mar 202429 Nov 202749.9 MW
East Claydon 132Kv S Stn (hybrid)20 Nov 202431 Oct 203799.8 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2026: 205 MW2027: 634 MW2037: 734 MW202620282030203220342037734 MW
0 MW400 MW800 MW2026: 205 MW2027: 634 MW2037: 734 MW20262029203220352037734 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026204.86 MW
2027634.36 MW
2037734.16 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1East Claydon 132Kv S Stn (solar)129.87 MW0 MW22 Oct 2026not statedgate not printedAccepted to Connect
2East Claydon 132Kv S Stn (solar)25 MW129.87 MW17 Nov 2026not statedgate not printedAccepted to Connect
3East Claydon 132Kv S Stn (solar)49.99 MW154.87 MW7 Dec 2026not statedgate not printedAccepted to Connect
4East Claydon 132Kv S Stn (solar)40 MW204.86 MW4 Jan 2027not statedgate not printedAccepted to Connect
5East Claydon 132Kv S Stn (solar)40 MW244.86 MW16 Feb 2027not statedgate not printedAccepted to Connect
6East Claydon 132Kv S Stn (bess)49.9 MW284.86 MW13 Apr 2027not statedgate not printedAccepted to Connect
7East Claydon 132Kv S Stn (hybrid)50 MW334.76 MW30 Apr 2027not statedgate not printedAccepted to Connect
8East Claydon 132Kv S Stn (solar)49.9 MW384.76 MW19 May 2027not statedgate not printedAccepted to Connect
9East Claydon 132Kv S Stn (bess)99.9 MW434.66 MW1 Jun 2027not statedgate not printedAccepted to Connect
10East Claydon 132Kv S Stn (solar)49.9 MW534.56 MW28 Jul 2027not statedgate not printedAccepted to Connect
11East Claydon 132Kv S Stn (bess)49.9 MW584.46 MW29 Nov 2027not statedgate not printedAccepted to Connect
12East Claydon 132Kv S Stn (hybrid)99.8 MW634.36 MW31 Oct 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20263204.86 MW
20278429.5 MW
2037199.8 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
East Claydon 132Kv S Stn (solar, 129.87 MW)Solar129.87 MW22 Oct 2026Accepted to Connect
East Claydon 132Kv S Stn (battery, 99.9 MW)Battery storage99.9 MW1 Jun 2027Accepted to Connect
East Claydon 132Kv S Stn (solar, 49.99 MW)Solar49.99 MW7 Dec 2026Accepted to Connect
East Claydon 132Kv S Stn (solar, 49.95 MW)Solar49.95 MW28 Jul 2027Accepted to Connect
East Claydon 132Kv S Stn (hybrid, 49.9 MW)Hybrid49.9 MW31 Oct 2037Accepted to Connect
East Claydon 132Kv S Stn (battery, 49.9 MW)Battery storage49.9 MW13 Apr 2027Accepted to Connect
East Claydon 132Kv S Stn (battery, 49.9 MW)Battery storage49.9 MW29 Nov 2027Accepted to Connect
East Claydon 132Kv S Stn (solar, 49.9 MW)Solar49.9 MW19 May 2027Accepted to Connect
East Claydon 132Kv S Stn (solar, 40 MW)Solar40 MW16 Feb 2027Accepted to Connect
East Claydon 132Kv S Stn (hybrid, 40 MW)Hybrid40 MW30 Apr 2027Accepted to Connect
East Claydon 132Kv S Stn (solar, 40 MW)Solar40 MW4 Jan 2027Accepted to Connect
East Claydon 132Kv S Stn (solar, 25 MW)Solar25 MW17 Nov 2026Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.