The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Enderby 132Kv S Stn (solar)
27 Jan 2021 to 12 Jun 2026, date already passed (gate not printed) - Enderby 132Kv S Stn (hybrid)
14 Oct 2022 to 11 Feb 2027 (gate not printed) - Enderby 132Kv S Stn (solar)
10 Nov 2020 to 30 Mar 2027 (gate not printed) - Enderby 132Kv S Stn (solar)
27 Apr 2023 to 6 Apr 2027 (gate not printed) - Enderby 132Kv S Stn (solar)
20 Oct 2025 to 7 Apr 2027 (gate not printed) - Enderby 132Kv S Stn (bess)
12 Jan 2023 to 13 May 2027 (gate not printed) - Enderby 132Kv S Stn (solar)
27 Apr 2022 to 11 Nov 2027 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Enderby 132Kv S Stn (solar) | 27 Jan 2021 | 12 Jun 2026 | 49.9 MW |
| Enderby 132Kv S Stn (hybrid) | 14 Oct 2022 | 11 Feb 2027 | 30 MW |
| Enderby 132Kv S Stn (solar) | 10 Nov 2020 | 30 Mar 2027 | 40 MW |
| Enderby 132Kv S Stn (solar) | 27 Apr 2023 | 6 Apr 2027 | 21 MW |
| Enderby 132Kv S Stn (solar) | 20 Oct 2025 | 7 Apr 2027 | 40 MW |
| Enderby 132Kv S Stn (bess) | 12 Jan 2023 | 13 May 2027 | 49.9 MW |
| Enderby 132Kv S Stn (solar) | 27 Apr 2022 | 11 Nov 2027 | 49.9 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 49.9 MW |
| 2027 | 280.7 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Enderby 132Kv S Stn (solar) | 49.9 MW | 0 MW | 12 Jun 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | Enderby 132Kv S Stn (hybrid) | 30 MW | 49.9 MW | 11 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 3 | Enderby 132Kv S Stn (solar) | 40 MW | 79.9 MW | 30 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 4 | Enderby 132Kv S Stn (solar) | 21 MW | 119.9 MW | 6 Apr 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | Enderby 132Kv S Stn (solar) | 40 MW | 140.9 MW | 7 Apr 2027 | not stated | gate not printed | Accepted to Connect |
| 6 | Enderby 132Kv S Stn (bess) | 49.9 MW | 180.9 MW | 13 May 2027 | not stated | gate not printed | Accepted to Connect |
| 7 | Enderby 132Kv S Stn (solar) | 49.9 MW | 230.8 MW | 11 Nov 2027 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 49.9 MW |
| 2027 | 6 | 230.8 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Enderby 132Kv S Stn (solar, 50 MW) | Solar | 50 MW | 12 Jun 2026 | Accepted to Connect |
| Enderby 132Kv S Stn (battery, 49.9 MW) | Battery storage | 49.9 MW | 13 May 2027 | Accepted to Connect |
| Enderby 132Kv S Stn (solar, 49.9 MW) | Solar | 49.9 MW | 11 Nov 2027 | Accepted to Connect |
| Enderby 132Kv S Stn (battery, 47.41 MW) | Battery storage | 47.41 MW | not stated | Connected |
| Enderby 132Kv S Stn (solar, 47.41 MW) | Solar | 47.41 MW | not stated | Connected |
| Enderby 132Kv S Stn (solar, 40 MW) | Solar | 40 MW | 7 Apr 2027 | Accepted to Connect |
| Enderby 132Kv S Stn (solar, 40 MW) | Solar | 40 MW | 30 Mar 2027 | Accepted to Connect |
| Enderby 132Kv S Stn (solar, 21 MW) | Solar | 21 MW | 6 Apr 2027 | Accepted to Connect |
| Enderby 132Kv S Stn (hybrid, 20 MW) | Hybrid | 20 MW | 11 Feb 2027 | Accepted to Connect |
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.