N84 Grid

Exeter Main Bsp

DNO substation.

Contracted here0.15 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date1 Feb 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue149 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Exeter Main Bsp (solar)16 Jul 20191 Feb 202735 MW
Exeter Main Bsp (hybrid)13 Jun 202325 Feb 202765 MW
Exeter Main Bsp (solar)16 Jan 20257 May 202727 MW
Exeter Main Bsp (bess)1 Jun 202330 Sep 202722 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 149 MW2027149 MW
0 MW100 MW200 MW2027: 149 MW2027149 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027149 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Exeter Main Bsp (solar)35 MW0 MW1 Feb 2027not statedgate not printedAccepted to Connect
2Exeter Main Bsp (hybrid)65 MW35 MW25 Feb 2027not statedgate not printedAccepted to Connect
3Exeter Main Bsp (solar)27 MW100 MW7 May 2027not statedgate not printedAccepted to Connect
4Exeter Main Bsp (bess)22 MW127 MW30 Sep 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20274149 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Exeter Main Bsp (hybrid, 49.9 MW)Hybrid49.9 MW25 Feb 2027Accepted to Connect
Exeter Main Bsp (solar, 35 MW)Solar35 MW1 Feb 2027Accepted to Connect
Exeter Main Bsp (solar, 27 MW)Solar27 MW7 May 2027Accepted to Connect
Exeter Main Bsp (solar, 10.36 MW)Solar10.36 MWnot statedConnected
Exeter Main Bsp (solar, 7.65 MW)Solar7.65 MWnot statedConnected
Exeter Main Bsp (solar, 3.95 MW)Solar3.95 MWnot statedConnected
Exeter Main Bsp (battery)Battery storage0 MW30 Sep 2027Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.