Fiskerton 33 11Kv S Stn

DNO substation.

Contracted here0.00 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date6 Sep 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue1.84 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Fiskerton 33 11Kv S Stn (solar)14 Mar 20256 Sep 20260.22 MW
Fiskerton 33 11Kv S Stn (solar)20 Oct 202529 Sep 20260.14 MW
Fiskerton 33 11Kv S Stn (solar)8 Dec 202220 Nov 20261 MW
Fiskerton 33 11Kv S Stn (solar)16 Jun 20222 Dec 20260.18 MW
Fiskerton 33 11Kv S Stn (solar)19 Dec 20222 Jun 20270.3 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1 MW2 MW2026: 2 MW2027: 2 MW202620272 MW
0 MW1 MW2 MW2026: 2 MW2027: 2 MW202620272 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20261.54 MW
20271.84 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Fiskerton 33 11Kv S Stn (solar)0.22 MW0 MW6 Sep 2026not statedgate not printedAccepted to Connect
2Fiskerton 33 11Kv S Stn (solar)0.14 MW0.22 MW29 Sep 2026not statedgate not printedAccepted to Connect
3Fiskerton 33 11Kv S Stn (solar)1 MW0.36 MW20 Nov 2026not statedgate not printedAccepted to Connect
4Fiskerton 33 11Kv S Stn (solar)0.18 MW1.36 MW2 Dec 2026not statedgate not printedAccepted to Connect
5Fiskerton 33 11Kv S Stn (solar)0.3 MW1.54 MW2 Jun 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202641.54 MW
202710.3 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Fiskerton 33 11Kv S Stn (solar, 1 MW)Solar1 MW20 Nov 2026Accepted to Connect
Fiskerton 33 11Kv S Stn (solar, 0.3 MW)Solar0.3 MW2 Jun 2027Accepted to Connect
Fiskerton 33 11Kv S Stn (solar, 0.22 MW)Solar0.22 MW6 Sep 2026Accepted to Connect
Fiskerton 33 11Kv S Stn (solar, 0.19 MW)Solar0.19 MWnot statedConnected
Fiskerton 33 11Kv S Stn (solar, 0.18 MW)Solar0.18 MW2 Dec 2026Accepted to Connect
Fiskerton 33 11Kv S Stn (solar, 0.14 MW)Solar0.14 MW29 Sep 2026Accepted to Connect
Fiskerton 33 11Kv S Stn (solar, 0.1 MW)Solar0.1 MWnot statedConnected
Fiskerton 33 11Kv S Stn (solar, 0.07 MW)Solar0.07 MWnot statedConnected
Fiskerton 33 11Kv S Stn (solar, 0.05 MW)Solar0.05 MWnot statedConnected