The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Grange (thermal)
16 Dec 2019 to 30 Nov 2026 (gate not printed) - Grange Bsp (solar)
23 Jan 2025 to 10 Oct 2027 (gate not printed) - Grange Bsp (thermal)
17 Jan 2025 to 17 Jan 2029 (gate not printed) - Grange (wind on)
18 Feb 2022 to 31 Aug 2030 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Grange (thermal) | 16 Dec 2019 | 30 Nov 2026 | 19 MW |
| Grange Bsp (solar) | 23 Jan 2025 | 10 Oct 2027 | 4.55 MW |
| Grange Bsp (thermal) | 17 Jan 2025 | 17 Jan 2029 | 22 MW |
| Grange (wind on) | 18 Feb 2022 | 31 Aug 2030 | 20.5 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 19 MW |
| 2027 | 23.55 MW |
| 2029 | 45.55 MW |
| 2030 | 66.05 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Grange (thermal) | 19 MW | 0 MW | 30 Nov 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | Grange Bsp (solar) | 4.55 MW | 19 MW | 10 Oct 2027 | not stated | gate not printed | Accepted to Connect |
| 3 | Grange Bsp (thermal) | 22 MW | 23.55 MW | 17 Jan 2029 | not stated | gate not printed | Accepted to Connect |
| 4 | Grange (wind on) | 20.5 MW | 45.55 MW | 31 Aug 2030 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 19 MW |
| 2027 | 1 | 4.55 MW |
| 2029 | 1 | 22 MW |
| 2030 | 1 | 20.5 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Grange Bsp (onshore wind, 32.02 MW) | Onshore wind | 32.02 MW | not stated | Connected |
| Grange Bsp (thermal, 22 MW) | Thermal | 22 MW | 17 Jan 2029 | Accepted to Connect |
| Grange Bsp (onshore wind, 20.5 MW) | Onshore wind | 20.5 MW | 31 Aug 2030 | Accepted to Connect |
| Grange Bsp (thermal, 19 MW) | Thermal | 19 MW | 30 Nov 2026 | Accepted to Connect |
| Grange Bsp (solar) | Solar | 0 MW | 10 Oct 2027 | Accepted to Connect |
Supported by NGED Open Data