The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Grendon 132Kv S Stn (bess)
21 May 2018 to 11 Nov 2026 (gate not printed) - Grendon 132Kv S Stn (solar)
20 Apr 2021 to 10 Dec 2026 (gate not printed) - Grendon 132Kv S Stn (solar)
21 Jun 2022 to 15 Feb 2027 (gate not printed) - Grendon 132Kv S Stn (solar)
18 Mar 2022 to 1 Mar 2027 (gate not printed) - Grendon 132Kv S Stn (solar)
4 Aug 2022 to 1 Mar 2027 (gate not printed) - Grendon 132Kv S Stn (solar)
15 Jul 2022 to 3 Mar 2027 (gate not printed) - Grendon 132Kv S Stn (solar)
4 Aug 2022 to 3 Mar 2027 (gate not printed) - Grendon 132Kv S Stn (hybrid)
11 May 2023 to 3 Mar 2027 (gate not printed) - Grendon 132Kv S Stn (hybrid)
23 Dec 2024 to 30 Mar 2027 (gate not printed) - Grendon 132Kv S Stn (solar)
3 Oct 2019 to 1 Apr 2027 (gate not printed) - Grendon 132Kv S Stn (solar)
9 Apr 2024 to 30 Apr 2027 (gate not printed) - Grendon 132Kv S Stn (hybrid)
24 Jan 2025 to 21 May 2027 (gate not printed) - Grendon 132Kv S Stn (solar)
22 Jan 2020 to 30 Jun 2027 (gate not printed) - Grendon 132Kv S Stn (solar)
2 Feb 2018 to 21 Sep 2027 (gate not printed) - Grendon 132Kv S Stn (solar)
10 Sep 2021 to 21 Sep 2027 (gate not printed) - Grendon 132Kv S Stn (hybrid)
11 May 2023 to 29 Nov 2027 (gate not printed) - Grendon 132Kv S Stn (bess)
26 Jan 2023 to 30 Nov 2027 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Grendon 132Kv S Stn (bess) | 21 May 2018 | 11 Nov 2026 | 49.9 MW |
| Grendon 132Kv S Stn (solar) | 20 Apr 2021 | 10 Dec 2026 | 30 MW |
| Grendon 132Kv S Stn (solar) | 21 Jun 2022 | 15 Feb 2027 | 35 MW |
| Grendon 132Kv S Stn (solar) | 18 Mar 2022 | 1 Mar 2027 | 35 MW |
| Grendon 132Kv S Stn (solar) | 4 Aug 2022 | 1 Mar 2027 | 80 MW |
| Grendon 132Kv S Stn (solar) | 15 Jul 2022 | 3 Mar 2027 | 49.9 MW |
| Grendon 132Kv S Stn (solar) | 4 Aug 2022 | 3 Mar 2027 | 39.3 MW |
| Grendon 132Kv S Stn (hybrid) | 11 May 2023 | 3 Mar 2027 | 100.13 MW |
| Grendon 132Kv S Stn (hybrid) | 23 Dec 2024 | 30 Mar 2027 | 99.8 MW |
| Grendon 132Kv S Stn (solar) | 3 Oct 2019 | 1 Apr 2027 | 40 MW |
| Grendon 132Kv S Stn (solar) | 9 Apr 2024 | 30 Apr 2027 | 36 MW |
| Grendon 132Kv S Stn (hybrid) | 24 Jan 2025 | 21 May 2027 | 69.9 MW |
| Grendon 132Kv S Stn (solar) | 22 Jan 2020 | 30 Jun 2027 | 60 MW |
| Grendon 132Kv S Stn (solar) | 2 Feb 2018 | 21 Sep 2027 | 40 MW |
| Grendon 132Kv S Stn (solar) | 10 Sep 2021 | 21 Sep 2027 | 36 MW |
| Grendon 132Kv S Stn (hybrid) | 11 May 2023 | 29 Nov 2027 | 100.13 MW |
| Grendon 132Kv S Stn (bess) | 26 Jan 2023 | 30 Nov 2027 | 99 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 79.9 MW |
| 2027 | 1,000.06 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Grendon 132Kv S Stn (bess) | 49.9 MW | 0 MW | 11 Nov 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | Grendon 132Kv S Stn (solar) | 30 MW | 49.9 MW | 10 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 3 | Grendon 132Kv S Stn (solar) | 35 MW | 79.9 MW | 15 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 4 | Grendon 132Kv S Stn (solar) | 35 MW | 114.9 MW | 1 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | Grendon 132Kv S Stn (solar) | 80 MW | 149.9 MW | 1 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 6 | Grendon 132Kv S Stn (solar) | 49.9 MW | 229.9 MW | 3 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 7 | Grendon 132Kv S Stn (solar) | 39.3 MW | 279.8 MW | 3 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 8 | Grendon 132Kv S Stn (hybrid) | 100.13 MW | 319.1 MW | 3 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 9 | Grendon 132Kv S Stn (hybrid) | 99.8 MW | 419.23 MW | 30 Mar 2027 | not stated | gate not printed | Accepted to Connect |
| 10 | Grendon 132Kv S Stn (solar) | 40 MW | 519.03 MW | 1 Apr 2027 | not stated | gate not printed | Accepted to Connect |
| 11 | Grendon 132Kv S Stn (solar) | 36 MW | 559.03 MW | 30 Apr 2027 | not stated | gate not printed | Accepted to Connect |
| 12 | Grendon 132Kv S Stn (hybrid) | 69.9 MW | 595.03 MW | 21 May 2027 | not stated | gate not printed | Accepted to Connect |
| 13 | Grendon 132Kv S Stn (solar) | 60 MW | 664.93 MW | 30 Jun 2027 | not stated | gate not printed | Accepted to Connect |
| 14 | Grendon 132Kv S Stn (solar) | 40 MW | 724.93 MW | 21 Sep 2027 | not stated | gate not printed | Accepted to Connect |
| 15 | Grendon 132Kv S Stn (solar) | 36 MW | 764.93 MW | 21 Sep 2027 | not stated | gate not printed | Accepted to Connect |
| 16 | Grendon 132Kv S Stn (hybrid) | 100.13 MW | 800.93 MW | 29 Nov 2027 | not stated | gate not printed | Accepted to Connect |
| 17 | Grendon 132Kv S Stn (bess) | 99 MW | 901.06 MW | 30 Nov 2027 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 2 | 79.9 MW |
| 2027 | 15 | 920.16 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Grendon 132Kv S Stn (battery, 99 MW) | Battery storage | 99 MW | 30 Nov 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar, 80 MW) | Solar | 80 MW | 1 Mar 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (hybrid, 60 MW) | Hybrid | 60 MW | 21 May 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar, 60 MW) | Solar | 60 MW | 30 Jun 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (hybrid, 49.9 MW) | Hybrid | 49.9 MW | 3 Mar 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar, 49.9 MW) | Solar | 49.9 MW | 3 Mar 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (battery, 49.9 MW) | Battery storage | 49.9 MW | 11 Nov 2026 | Accepted to Connect |
| Grendon 132Kv S Stn (hybrid, 49.9 MW) | Hybrid | 49.9 MW | 29 Nov 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (hybrid, 49.9 MW) | Hybrid | 49.9 MW | 30 Mar 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar, 40 MW) | Solar | 40 MW | 21 Sep 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar, 40 MW) | Solar | 40 MW | 1 Apr 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar, 39.3 MW) | Solar | 39.3 MW | 3 Mar 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar, 36 MW) | Solar | 36 MW | 30 Apr 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar, 36 MW) | Solar | 36 MW | 21 Sep 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar, 35 MW) | Solar | 35 MW | 15 Feb 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar, 35 MW) | Solar | 35 MW | 1 Mar 2027 | Accepted to Connect |
| Grendon 132Kv S Stn (solar) | Solar | 0 MW | 10 Dec 2026 | Accepted to Connect |