N84 Grid

Hinckley 11Kv S Stn

DNO substation.

Contracted here0.09 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date11 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue92.48 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Hinckley 11Kv S Stn (solar)21 Aug 202011 Dec 20262.15 MW
Hinckley 33Kv S Stn (gas)23 Dec 20198 Mar 20278 MW
Hinckley 33Kv S Stn (solar)22 Mar 202212 May 20270.1 MW
Hinckley 33Kv S Stn (solar)26 Feb 202025 May 202720 MW
Hinckley 33Kv S Stn (solar)26 Nov 20244 Oct 202720 MW
Hinckley 33Kv S Stn (solar)19 Feb 20241 Oct 203142.23 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2026: 2 MW2027: 50 MW2031: 92 MW20262027202820292030203192 MW
0 MW50 MW100 MW2026: 2 MW2027: 50 MW2031: 92 MW202620282030203192 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20262.15 MW
202750.25 MW
203192.48 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Hinckley 11Kv S Stn (solar)2.15 MW0 MW11 Dec 2026not statedgate not printedAccepted to Connect
2Hinckley 33Kv S Stn (gas)8 MW2.15 MW8 Mar 2027not statedgate not printedAccepted to Connect
3Hinckley 33Kv S Stn (solar)0.1 MW10.15 MW12 May 2027not statedgate not printedAccepted to Connect
4Hinckley 33Kv S Stn (solar)20 MW10.25 MW25 May 2027not statedgate not printedAccepted to Connect
5Hinckley 33Kv S Stn (solar)20 MW30.25 MW4 Oct 2027not statedgate not printedAccepted to Connect
6Hinckley 33Kv S Stn (solar)42.23 MW50.25 MW1 Oct 2031not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202612.15 MW
2027448.1 MW
2031142.23 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Hinckley 11Kv S Stn (solar, 20 MW)Solar20 MW25 May 2027Accepted to Connect
Hinckley 11Kv S Stn (solar, 20 MW)Solar20 MW4 Oct 2027Accepted to Connect
Hinckley 11Kv S Stn (solar, 14.25 MW)Solar14.25 MWnot statedConnected
Hinckley 11Kv S Stn (gas, 8 MW)Gas8 MWnot statedConnected
Hinckley 11Kv S Stn (gas, 8 MW)Gas8 MWnot statedConnected
Hinckley 11Kv S Stn (gas, 8 MW)Gas8 MW8 Mar 2027Accepted to Connect
Hinckley 11Kv S Stn (solar, 2.15 MW)Solar2.15 MW11 Dec 2026Accepted to Connect
Hinckley 11Kv S Stn (solar, 0.67 MW)Solar0.67 MWnot statedConnected
Hinckley 11Kv S Stn (solar, 0.47 MW)Solar0.47 MWnot statedConnected
Hinckley 11Kv S Stn (solar, 0.38 MW)Solar0.38 MWnot statedConnected
Hinckley 11Kv S Stn (solar, 0.34 MW)Solar0.34 MWnot statedConnected
Hinckley 11Kv S Stn (other, 0.31 MW)Other0.31 MWnot statedConnected
Hinckley 11Kv S Stn (solar, 0.24 MW)Solar0.24 MWnot statedConnected
Hinckley 11Kv S Stn (solar, 0.23 MW)Solar0.23 MWnot statedConnected
Hinckley 11Kv S Stn (solar, 0.14 MW)Solar0.14 MWnot statedConnected
Hinckley 11Kv S Stn (solar, 0.1 MW)Solar0.1 MWnot statedConnected
Hinckley 11Kv S Stn (solar, 0.1 MW)Solar0.1 MW12 May 2027Accepted to Connect
Hinckley 11Kv S Stn (solar, 0.05 MW)Solar0.05 MWnot statedConnected
Hinckley 11Kv S Stn (solar, 0.05 MW)Solar0.05 MWnot statedConnected
Hinckley 11Kv S Stn (solar, 0.05 MW)Solar0.05 MWnot statedConnected
Hinckley 11Kv S Stn (solar)Solar0 MW1 Oct 2031Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.