The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Hinksford 132Kv S Stn (solar)
20 Mar 2026 to 22 Jun 2029 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Hinksford 132Kv S Stn (solar) | 20 Mar 2026 | 22 Jun 2029 | 35 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2029 | 35 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Hinksford 132Kv S Stn (solar) | 35 MW | 0 MW | 22 Jun 2029 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2029 | 1 | 35 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Hinksford 132Kv S Stn (solar, 35 MW) | Solar | 35 MW | 22 Jun 2029 | Accepted to Connect |
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.