Indian Queens Sgp

DNO substation.

Contracted here0.53 GWNot yet connected, as printed
Entries in the queue10entries with a printed MW
Earliest connection date6 Jan 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue256.4 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Indian Queens Sgp (solar)12 Aug 20226 Jan 202749.9 MW
Indian Queens Sgp (wind off)11 Apr 201919 Jan 202720 MW
Indian Queens Sgp (solar)13 Nov 20204 Mar 202757 MW
Indian Queens Sgp (bess)13 Oct 20214 Mar 202749.5 MW
Indian Queens Sgp (solar)8 Aug 201823 Mar 202730 MW
Indian Queens Sgp (solar)11 Nov 20244 May 202750 MW
Indian Queens Sgp (hybrid)19 Mar 20249 Jul 202799.8 MW
Indian Queens Sgp (hybrid)8 Apr 202419 Jul 202750 MW
Indian Queens Sgp (bess)5 Apr 202429 Jul 202799.9 MW
Indian Queens Sgp (wind on)19 May 202527 Sep 202725.3 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2027: 531 MW2027531 MW
0 MW400 MW800 MW2027: 531 MW2027531 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027531.4 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Indian Queens Sgp (solar)49.9 MW0 MW6 Jan 2027not statedgate not printedAccepted to Connect
2Indian Queens Sgp (wind off)20 MW49.9 MW19 Jan 2027not statedgate not printedAccepted to Connect
3Indian Queens Sgp (solar)57 MW69.9 MW4 Mar 2027not statedgate not printedAccepted to Connect
4Indian Queens Sgp (bess)49.5 MW126.9 MW4 Mar 2027not statedgate not printedAccepted to Connect
5Indian Queens Sgp (solar)30 MW176.4 MW23 Mar 2027not statedgate not printedAccepted to Connect
6Indian Queens Sgp (solar)50 MW206.4 MW4 May 2027not statedgate not printedAccepted to Connect
7Indian Queens Sgp (hybrid)99.8 MW256.4 MW9 Jul 2027not statedgate not printedAccepted to Connect
8Indian Queens Sgp (hybrid)50 MW356.2 MW19 Jul 2027not statedgate not printedAccepted to Connect
9Indian Queens Sgp (bess)99.9 MW406.2 MW29 Jul 2027not statedgate not printedAccepted to Connect
10Indian Queens Sgp (wind on)25.3 MW506.1 MW27 Sep 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202710531.4 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Indian Queens Sgp (battery, 99.9 MW)Battery storage99.9 MW29 Jul 2027Accepted to Connect
Indian Queens Sgp (solar, 50 MW)Solar50 MW4 May 2027Accepted to Connect
Indian Queens Sgp (hybrid, 49.9 MW)Hybrid49.9 MW9 Jul 2027Accepted to Connect
Indian Queens Sgp (solar, 49.9 MW)Solar49.9 MW6 Jan 2027Accepted to Connect
Indian Queens Sgp (battery, 49.5 MW)Battery storage49.5 MW4 Mar 2027Accepted to Connect
Indian Queens Sgp (solar, 48.37 MW)Solar48.37 MWnot statedConnected
Indian Queens Sgp (solar, 44 MW)Solar44 MW4 Mar 2027Accepted to Connect
Indian Queens Sgp (solar, 30 MW)Solar30 MW23 Mar 2027Accepted to Connect
Indian Queens Sgp (hybrid, 25.61 MW)Hybrid25.61 MWnot statedConnected
Indian Queens Sgp (onshore wind, 25.3 MW)Onshore wind25.3 MW27 Sep 2027Accepted to Connect
Indian Queens Sgp (hybrid, 25 MW)Hybrid25 MW19 Jul 2027Accepted to Connect
Indian Queens Sgp (thermal, 24.1 MW)Thermal24.1 MWnot statedConnected
Indian Queens Sgp (offshore wind, 20 MW)Offshore wind20 MW19 Jan 2027Accepted to Connect