N84 Grid

Lampeter Primary

DNO substation.

Contracted here0.03 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date1 Sep 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue34.85 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lampeter Primary (wind on)5 Sep 20231 Sep 20260.9 MW
Lampeter Primary (solar)6 Jan 20255 Dec 20260.07 MW
Lampeter Primary (wind on)6 Mar 201330 Dec 20265 MW
Lampeter Grid (wind on)24 Nov 202031 Jan 203025.2 MW
Lampeter Grid (wind on)20 Nov 202531 Jan 20303.68 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW20 MW40 MW2026: 6 MW2030: 35 MW2026202720282029203035 MW
0 MW20 MW40 MW2026: 6 MW2030: 35 MW20262028203035 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20265.97 MW
203034.85 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lampeter Primary (wind on)0.9 MW0 MW1 Sep 2026not statedgate not printedAccepted to Connect
2Lampeter Primary (solar)0.07 MW0.9 MW5 Dec 2026not statedgate not printedAccepted to Connect
3Lampeter Primary (wind on)5 MW0.97 MW30 Dec 2026not statedgate not printedAccepted to Connect
4Lampeter Grid (wind on)25.2 MW5.97 MW31 Jan 2030not statedgate not printedAccepted to Connect
5Lampeter Grid (wind on)3.68 MW31.17 MW31 Jan 2030not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202635.97 MW
2030228.88 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Lampeter Primary (onshore wind, 25.2 MW)Onshore wind25.2 MW31 Jan 2030Accepted to Connect
Lampeter Primary (onshore wind, 5 MW)Onshore wind5 MW30 Dec 2026Accepted to Connect
Lampeter Primary (solar, 3.99 MW)Solar3.99 MWnot statedConnected
Lampeter Primary (onshore wind, 3.68 MW)Onshore wind3.68 MW31 Jan 2030Accepted to Connect
Lampeter Primary (onshore wind, 0.9 MW)Onshore wind0.9 MW1 Sep 2026Accepted to Connect
Lampeter Primary (onshore wind, 0.5 MW)Onshore wind0.5 MWnot statedConnected
Lampeter Primary (onshore wind, 0.48 MW)Onshore wind0.48 MWnot statedConnected
Lampeter Primary (solar, 0.14 MW)Solar0.14 MWnot statedConnected
Lampeter Primary (onshore wind, 0.09 MW)Onshore wind0.09 MWnot statedConnected
Lampeter Primary (onshore wind, 0.09 MW)Onshore wind0.09 MWnot statedConnected
Lampeter Primary (solar, 0.07 MW)Solar0.07 MW5 Dec 2026Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.