N84 Grid

Landulph Bsp

DNO substation.

Contracted here0.20 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date3 Feb 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue197.87 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Landulph Bsp (bess)14 Nov 20213 Feb 202749.9 MW
Landulph Bsp (solar)22 Aug 20236 Apr 20277.8 MW
Landulph Bsp (bess)29 Jul 20224 May 202780 MW
Landulph Bsp (solar)23 Feb 202216 Sep 202749.92 MW
Landulph Bsp (solar)5 Jan 202329 Sep 20275.25 MW
Landulph Bsp (solar)7 Jun 202329 Sep 20275 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 198 MW2027198 MW
0 MW100 MW200 MW2027: 198 MW2027198 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027197.87 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Landulph Bsp (bess)49.9 MW0 MW3 Feb 2027not statedgate not printedAccepted to Connect
2Landulph Bsp (solar)7.8 MW49.9 MW6 Apr 2027not statedgate not printedAccepted to Connect
3Landulph Bsp (bess)80 MW57.7 MW4 May 2027not statedgate not printedAccepted to Connect
4Landulph Bsp (solar)49.92 MW137.7 MW16 Sep 2027not statedgate not printedAccepted to Connect
5Landulph Bsp (solar)5.25 MW187.62 MW29 Sep 2027not statedgate not printedAccepted to Connect
6Landulph Bsp (solar)5 MW192.87 MW29 Sep 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20276197.87 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Landulph Bsp (battery, 80 MW)Battery storage80 MW4 May 2027Accepted to Connect
Landulph Bsp (solar, 49.92 MW)Solar49.92 MW16 Sep 2027Accepted to Connect
Landulph Bsp (battery, 49.9 MW)Battery storage49.9 MW3 Feb 2027Accepted to Connect
Landulph Bsp (solar, 15.68 MW)Solar15.68 MWnot statedConnected
Landulph Bsp (solar, 7.8 MW)Solar7.8 MW6 Apr 2027Accepted to Connect
Landulph Bsp (solar, 6.34 MW)Solar6.34 MWnot statedConnected
Landulph Bsp (solar, 5.25 MW)Solar5.25 MW29 Sep 2027Accepted to Connect
Landulph Bsp (solar, 5 MW)Solar5 MW29 Sep 2027Accepted to Connect
Landulph Bsp (solar, 4.75 MW)Solar4.75 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.