Lawes Bridge

DNO substation.

Contracted here0.00 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date1 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue4.15 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lawes Bridge (solar)18 Oct 20221 Dec 20263.2 MW
Lawes Bridge (solar)14 Feb 202631 Dec 20320.95 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW3 MW5 MW2026: 3 MW2032: 4 MW20262027202820292030203120324 MW
0 MW3 MW5 MW2026: 3 MW2032: 4 MW20262028203020324 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20263.2 MW
20324.15 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lawes Bridge (solar)3.2 MW0 MW1 Dec 2026not statedgate not printedAccepted to Connect
2Lawes Bridge (solar)0.95 MW3.2 MW31 Dec 2032not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202613.2 MW
203210.95 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Lawes Bridge (solar, 1 MW)Solar1 MW1 Dec 2026Accepted to Connect
Lawes Bridge (solar, 0.95 MW)Solar0.95 MW31 Dec 2032Accepted to Connect
Lawes Bridge (hybrid, 0.3 MW)Hybrid0.3 MWnot statedConnected
Lawes Bridge (solar, 0.05 MW)Solar0.05 MWnot statedConnected