Lea Marston 132Kv S Stn

DNO substation.

Contracted here0.57 GWNot yet connected, as printed
Entries in the queue8entries with a printed MW
Earliest connection date18 Nov 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue476.6 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lea Marston 132Kv S Stn (solar)11 Aug 202018 Nov 202649.9 MW
Lea Marston 132Kv S Stn (solar)14 Aug 202522 Dec 202650 MW
Lea Marston 132Kv S Stn (bess)22 Jan 202211 Jan 202798 MW
Lea Marston 132Kv S Stn (thermal)10 Aug 20202 Feb 202729 MW
Lea Marston 132Kv S Stn (hybrid)2 Jan 202415 Feb 2027199.8 MW
Lea Marston 132Kv S Stn (solar)23 Mar 202230 Apr 202749.9 MW
Lea Marston 132Kv S Stn (solar)18 Jan 202410 Aug 202749.9 MW
Lea Marston 132Kv S Stn (solar)13 Feb 20256 Nov 203744 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2026: 100 MW2027: 527 MW2037: 571 MW202620282030203220342037571 MW
0 MW400 MW800 MW2026: 100 MW2027: 527 MW2037: 571 MW20262029203220352037571 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202699.9 MW
2027526.5 MW
2037570.5 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lea Marston 132Kv S Stn (solar)49.9 MW0 MW18 Nov 2026not statedgate not printedAccepted to Connect
2Lea Marston 132Kv S Stn (solar)50 MW49.9 MW22 Dec 2026not statedgate not printedAccepted to Connect
3Lea Marston 132Kv S Stn (bess)98 MW99.9 MW11 Jan 2027not statedgate not printedAccepted to Connect
4Lea Marston 132Kv S Stn (thermal)29 MW197.9 MW2 Feb 2027not statedgate not printedAccepted to Connect
5Lea Marston 132Kv S Stn (hybrid)199.8 MW226.9 MW15 Feb 2027not statedgate not printedAccepted to Connect
6Lea Marston 132Kv S Stn (solar)49.9 MW426.7 MW30 Apr 2027not statedgate not printedAccepted to Connect
7Lea Marston 132Kv S Stn (solar)49.9 MW476.6 MW10 Aug 2027not statedgate not printedAccepted to Connect
8Lea Marston 132Kv S Stn (solar)44 MW526.5 MW6 Nov 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026299.9 MW
20275426.6 MW
2037144 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Lea Marston 132Kv S Stn (hybrid, 99.9 MW)Hybrid99.9 MW15 Feb 2027Accepted to Connect
Lea Marston 132Kv S Stn (battery, 98 MW)Battery storage98 MW11 Jan 2027Accepted to Connect
Lea Marston 132Kv S Stn (solar, 50 MW)Solar50 MW22 Dec 2026Accepted to Connect
Lea Marston 132Kv S Stn (solar, 49.9 MW)Solar49.9 MW18 Nov 2026Accepted to Connect
Lea Marston 132Kv S Stn (solar, 49.9 MW)Solar49.9 MW10 Aug 2027Accepted to Connect
Lea Marston 132Kv S Stn (solar, 49 MW)Solar49 MW30 Apr 2027Accepted to Connect
Lea Marston 132Kv S Stn (solar, 44 MW)Solar44 MW6 Nov 2037Accepted to Connect
Lea Marston 132Kv S Stn (thermal, 29 MW)Thermal29 MW2 Feb 2027Accepted to Connect