N84 Grid

Llandyfaelog Gsp

DNO substation.

Contracted here0.42 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue424 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Llandyfaelog Gsp (wind on)6 Apr 202331 Dec 2026175 MW
Llandyfaelog Gsp (hybrid)7 Jun 20227 Sep 2027121.2 MW
Llandyfaelog Gsp (bess)11 Feb 202530 Nov 203087.8 MW
Llandyfaelog Gsp (solar)15 Aug 20246 Dec 203640 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW250 MW500 MW2026: 175 MW2027: 296 MW2030: 384 MW2036: 424 MW202620282030203220342036424 MW
0 MW250 MW500 MW2026: 175 MW2027: 296 MW2030: 384 MW2036: 424 MW2026202920322036424 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026175 MW
2027296.2 MW
2030384 MW
2036424 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Llandyfaelog Gsp (wind on)175 MW0 MW31 Dec 2026not statedgate not printedAccepted to Connect
2Llandyfaelog Gsp (hybrid)121.2 MW175 MW7 Sep 2027not statedgate not printedAccepted to Connect
3Llandyfaelog Gsp (bess)87.8 MW296.2 MW30 Nov 2030not statedgate not printedAccepted to Connect
4Llandyfaelog Gsp (solar)40 MW384 MW6 Dec 2036not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20261175 MW
20271121.2 MW
2030187.8 MW
2036140 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Llandyfaelog Gsp (onshore wind, 175 MW)Onshore wind175 MW31 Dec 2026Accepted to Connect
Llandyfaelog Gsp (hybrid, 110.8 MW)Hybrid110.8 MW7 Sep 2027Accepted to Connect
Llandyfaelog Gsp (battery, 87.8 MW)Battery storage87.8 MW30 Nov 2030Accepted to Connect
Llandyfaelog Gsp (solar, 40 MW)Solar40 MW6 Dec 2036Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.