N84 Grid

Metheringham 33 11Kv S Stn

DNO substation.

Contracted here0.00 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date16 Sep 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue4.88 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Metheringham 33 11Kv S Stn (solar)22 Sep 202116 Sep 20260.13 MW
Metheringham 33 11Kv S Stn (solar)24 Sep 20249 Oct 20261.7 MW
Metheringham 33 11Kv S Stn (solar)6 Dec 202220 Nov 20260.25 MW
Metheringham 33 11Kv S Stn (solar)13 Oct 20222 Dec 20260.1 MW
Metheringham 33 11Kv S Stn (hybrid)8 Sep 20232 Jun 20272.7 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW3 MW5 MW2026: 2 MW2027: 5 MW202620275 MW
0 MW3 MW5 MW2026: 2 MW2027: 5 MW202620275 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20262.18 MW
20274.88 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Metheringham 33 11Kv S Stn (solar)0.13 MW0 MW16 Sep 2026not statedgate not printedAccepted to Connect
2Metheringham 33 11Kv S Stn (solar)1.7 MW0.13 MW9 Oct 2026not statedgate not printedAccepted to Connect
3Metheringham 33 11Kv S Stn (solar)0.25 MW1.83 MW20 Nov 2026not statedgate not printedAccepted to Connect
4Metheringham 33 11Kv S Stn (solar)0.1 MW2.08 MW2 Dec 2026not statedgate not printedAccepted to Connect
5Metheringham 33 11Kv S Stn (hybrid)2.7 MW2.18 MW2 Jun 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202642.18 MW
202712.7 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Metheringham 33 11Kv S Stn (hybrid, 2 MW)Hybrid2 MW2 Jun 2027Accepted to Connect
Metheringham 33 11Kv S Stn (thermal, 1.9 MW)Thermal1.9 MWnot statedConnected
Metheringham 33 11Kv S Stn (solar, 0.25 MW)Solar0.25 MW20 Nov 2026Accepted to Connect
Metheringham 33 11Kv S Stn (solar, 0.24 MW)Solar0.24 MWnot statedConnected
Metheringham 33 11Kv S Stn (solar, 0.24 MW)Solar0.24 MWnot statedConnected
Metheringham 33 11Kv S Stn (solar, 0.24 MW)Solar0.24 MWnot statedConnected
Metheringham 33 11Kv S Stn (gas, 0.19 MW)Gas0.19 MWnot statedConnected
Metheringham 33 11Kv S Stn (solar, 0.19 MW)Solar0.19 MWnot statedConnected
Metheringham 33 11Kv S Stn (solar, 0.13 MW)Solar0.13 MW16 Sep 2026Accepted to Connect
Metheringham 33 11Kv S Stn (solar, 0.13 MW)Solar0.13 MWnot statedConnected
Metheringham 33 11Kv S Stn (solar, 0.1 MW)Solar0.1 MW2 Dec 2026Accepted to Connect
Metheringham 33 11Kv S Stn (solar)Solar0 MW9 Oct 2026Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.