Mountain Ash Grid

DNO substation.

Contracted here0.06 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date14 Apr 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue59.63 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Mountain Ash Grid (solar)4 Dec 202514 Apr 202730 MW
Mountain Ash Grid (solar)29 Jan 20269 Jul 202711 MW
Mountain Ash Grid (wind on)16 Jun 202531 Oct 203718 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW40 MW80 MW2027: 41 MW2037: 59 MW20272029203120332035203759 MW
0 MW40 MW80 MW2027: 41 MW2037: 59 MW202720302033203759 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202741 MW
203759 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Mountain Ash Grid (solar)30 MW0 MW14 Apr 2027not statedgate not printedAccepted to Connect
2Mountain Ash Grid (solar)11 MW30 MW9 Jul 2027not statedgate not printedAccepted to Connect
3Mountain Ash Grid (wind on)18 MW41 MW31 Oct 2037not statedgate not printedAccepted to Connect
4Mountain Ash (solar)0.63 MW59 MWnot statednot statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027241 MW
2037118 MW
not stated10.63 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Mountain Ash Grid (solar, 30 MW)Solar30 MW14 Apr 2027Accepted to Connect
Mountain Ash Grid (onshore wind, 18 MW)Onshore wind18 MW31 Oct 2037Accepted to Connect
Mountain Ash Grid (gas, 16.72 MW)Gas16.72 MWnot statedConnected
Mountain Ash Grid (solar, 11 MW)Solar11 MW9 Jul 2027Accepted to Connect
Mountain Ash Grid (solar, 3.91 MW)Solar3.91 MWnot statedConnected
Mountain Ash Grid (solar, 0.1 MW)Solar0.1 MWnot statedAccepted to Connect
Mountain Ash Grid (solar, 0.08 MW)Solar0.08 MWnot statedConnected