The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Nuneaton 33Kv S Stn (solar)
4 Aug 2022 to 30 Nov 2026 (gate not printed) - Nuneaton 33Kv S Stn (solar)
13 Jul 2023 to 12 Jan 2027 (gate not printed) - Nuneaton 33Kv S Stn (solar)
26 Oct 2020 to 1 Feb 2027 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Nuneaton 33Kv S Stn (solar) | 4 Aug 2022 | 30 Nov 2026 | 40 MW |
| Nuneaton 33Kv S Stn (solar) | 13 Jul 2023 | 12 Jan 2027 | 20 MW |
| Nuneaton 33Kv S Stn (solar) | 26 Oct 2020 | 1 Feb 2027 | 12.8 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 40 MW |
| 2027 | 72.8 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Nuneaton 33Kv S Stn (solar) | 40 MW | 0 MW | 30 Nov 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | Nuneaton 33Kv S Stn (solar) | 20 MW | 40 MW | 12 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 3 | Nuneaton 33Kv S Stn (solar) | 12.8 MW | 60 MW | 1 Feb 2027 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 40 MW |
| 2027 | 2 | 32.8 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Nuneaton 11Kv S Stn (solar, 40 MW) | Solar | 40 MW | 30 Nov 2026 | Accepted to Connect |
| Nuneaton 11Kv S Stn (solar, 20 MW) | Solar | 20 MW | 12 Jan 2027 | Accepted to Connect |
| Nuneaton 11Kv S Stn (solar, 19 MW) | Solar | 19 MW | not stated | Connected |
| Nuneaton 11Kv S Stn (solar, 12.8 MW) | Solar | 12.8 MW | 1 Feb 2027 | Accepted to Connect |
| Nuneaton 11Kv S Stn (thermal, 1.14 MW) | Thermal | 1.14 MW | not stated | Connected |
| Nuneaton 11Kv S Stn (solar, 0.1 MW) | Solar | 0.1 MW | not stated | Connected |
| Nuneaton 11Kv S Stn (solar, 0.08 MW) | Solar | 0.08 MW | not stated | Connected |
| Nuneaton 11Kv S Stn (solar, 0.06 MW) | Solar | 0.06 MW | not stated | Connected |
| Nuneaton 11Kv S Stn (solar, 0.06 MW) | Solar | 0.06 MW | not stated | Connected |
Supported by NGED Open Data