The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Port Ham 132Kv S Stn (solar)
3 Apr 2020 to 13 Oct 2026, date already passed (gate not printed) - Port Ham 132Kv S Stn (solar)
24 Jun 2019 to 1 Dec 2026 (gate not printed) - Port Ham 132Kv S Stn (solar)
28 Jan 2022 to 23 Dec 2026 (gate not printed) - Port Ham 132Kv S Stn (solar)
8 Jul 2021 to 7 Jan 2027 (gate not printed) - Port Ham 132Kv S Stn (solar)
4 Feb 2019 to 21 Jan 2027 (gate not printed) - Port Ham 132Kv S Stn (bess)
4 Feb 2022 to 26 Jan 2027 (gate not printed) - Port Ham 132Kv S Stn (bess)
20 May 2021 to 28 Jan 2027 (gate not printed) - Port Ham 132Kv S Stn (bess)
17 Mar 2023 to 11 Feb 2027 (gate not printed) - Port Ham 132Kv S Stn (bess)
20 Sep 2023 to 11 Feb 2027 (gate not printed) - Port Ham 132Kv S Stn (solar)
21 Mar 2022 to 12 Feb 2027 (gate not printed) - Port Ham 132Kv S Stn (solar)
3 May 2022 to 16 Feb 2027 (gate not printed) - Port Ham 132Kv S Stn (solar)
7 Apr 2022 to 30 Dec 2027 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Port Ham 132Kv S Stn (solar) | 3 Apr 2020 | 13 Oct 2026 | 45 MW |
| Port Ham 132Kv S Stn (solar) | 24 Jun 2019 | 1 Dec 2026 | 49.9 MW |
| Port Ham 132Kv S Stn (solar) | 28 Jan 2022 | 23 Dec 2026 | 49.5 MW |
| Port Ham 132Kv S Stn (solar) | 8 Jul 2021 | 7 Jan 2027 | 60 MW |
| Port Ham 132Kv S Stn (solar) | 4 Feb 2019 | 21 Jan 2027 | 40 MW |
| Port Ham 132Kv S Stn (bess) | 4 Feb 2022 | 26 Jan 2027 | 99.9 MW |
| Port Ham 132Kv S Stn (bess) | 20 May 2021 | 28 Jan 2027 | 49.9 MW |
| Port Ham 132Kv S Stn (bess) | 17 Mar 2023 | 11 Feb 2027 | 49.9 MW |
| Port Ham 132Kv S Stn (bess) | 20 Sep 2023 | 11 Feb 2027 | 40 MW |
| Port Ham 132Kv S Stn (solar) | 21 Mar 2022 | 12 Feb 2027 | 40 MW |
| Port Ham 132Kv S Stn (solar) | 3 May 2022 | 16 Feb 2027 | 49.5 MW |
| Port Ham 132Kv S Stn (solar) | 7 Apr 2022 | 30 Dec 2027 | 99 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 144.4 MW |
| 2027 | 672.6 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Port Ham 132Kv S Stn (solar) | 45 MW | 0 MW | 13 Oct 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | Port Ham 132Kv S Stn (solar) | 49.9 MW | 45 MW | 1 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 3 | Port Ham 132Kv S Stn (solar) | 49.5 MW | 94.9 MW | 23 Dec 2026 | not stated | gate not printed | Accepted to Connect |
| 4 | Port Ham 132Kv S Stn (solar) | 60 MW | 144.4 MW | 7 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | Port Ham 132Kv S Stn (solar) | 40 MW | 204.4 MW | 21 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 6 | Port Ham 132Kv S Stn (bess) | 99.9 MW | 244.4 MW | 26 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 7 | Port Ham 132Kv S Stn (bess) | 49.9 MW | 344.3 MW | 28 Jan 2027 | not stated | gate not printed | Accepted to Connect |
| 8 | Port Ham 132Kv S Stn (bess) | 49.9 MW | 394.2 MW | 11 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 9 | Port Ham 132Kv S Stn (bess) | 40 MW | 444.1 MW | 11 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 10 | Port Ham 132Kv S Stn (solar) | 40 MW | 484.1 MW | 12 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 11 | Port Ham 132Kv S Stn (solar) | 49.5 MW | 524.1 MW | 16 Feb 2027 | not stated | gate not printed | Accepted to Connect |
| 12 | Port Ham 132Kv S Stn (solar) | 99 MW | 573.6 MW | 30 Dec 2027 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 3 | 144.4 MW |
| 2027 | 9 | 528.2 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Port Ham 132Kv S Stn (battery, 99.9 MW) | Battery storage | 99.9 MW | 26 Jan 2027 | Accepted to Connect |
| Port Ham 132Kv S Stn (solar, 99 MW) | Solar | 99 MW | 30 Dec 2027 | Accepted to Connect |
| Port Ham 132Kv S Stn (battery, 49.9 MW) | Battery storage | 49.9 MW | 28 Jan 2027 | Accepted to Connect |
| Port Ham 132Kv S Stn (battery, 49.9 MW) | Battery storage | 49.9 MW | 11 Feb 2027 | Accepted to Connect |
| Port Ham 132Kv S Stn (solar, 49.9 MW) | Solar | 49.9 MW | 1 Dec 2026 | Accepted to Connect |
| Port Ham 132Kv S Stn (solar, 49.5 MW) | Solar | 49.5 MW | 16 Feb 2027 | Accepted to Connect |
| Port Ham 132Kv S Stn (solar, 49.5 MW) | Solar | 49.5 MW | 23 Dec 2026 | Accepted to Connect |
| Port Ham 132Kv S Stn (solar, 47.41 MW) | Solar | 47.41 MW | not stated | Connected |
| Port Ham 132Kv S Stn (solar, 47.41 MW) | Solar | 47.41 MW | not stated | Connected |
| Port Ham 132Kv S Stn (solar, 45 MW) | Solar | 45 MW | 13 Oct 2026 | Accepted to Connect |
| Port Ham 132Kv S Stn (solar, 40 MW) | Solar | 40 MW | 12 Feb 2027 | Accepted to Connect |
| Port Ham 132Kv S Stn (solar, 40 MW) | Solar | 40 MW | 21 Jan 2027 | Accepted to Connect |
| Port Ham 132Kv S Stn (solar, 40 MW) | Solar | 40 MW | 7 Jan 2027 | Accepted to Connect |
| Port Ham 132Kv S Stn (battery, 40 MW) | Battery storage | 40 MW | 11 Feb 2027 | Accepted to Connect |
| Port Ham 132Kv S Stn (solar, 23.75 MW) | Solar | 23.75 MW | not stated | Connected |