N84 Grid

Port Ham 132Kv S Stn

DNO substation.

Contracted here0.67 GWNot yet connected, as printed
Entries in the queue12entries with a printed MW
Earliest connection date13 Oct 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue344.3 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Port Ham 132Kv S Stn (solar)3 Apr 202013 Oct 202645 MW
Port Ham 132Kv S Stn (solar)24 Jun 20191 Dec 202649.9 MW
Port Ham 132Kv S Stn (solar)28 Jan 202223 Dec 202649.5 MW
Port Ham 132Kv S Stn (solar)8 Jul 20217 Jan 202760 MW
Port Ham 132Kv S Stn (solar)4 Feb 201921 Jan 202740 MW
Port Ham 132Kv S Stn (bess)4 Feb 202226 Jan 202799.9 MW
Port Ham 132Kv S Stn (bess)20 May 202128 Jan 202749.9 MW
Port Ham 132Kv S Stn (bess)17 Mar 202311 Feb 202749.9 MW
Port Ham 132Kv S Stn (bess)20 Sep 202311 Feb 202740 MW
Port Ham 132Kv S Stn (solar)21 Mar 202212 Feb 202740 MW
Port Ham 132Kv S Stn (solar)3 May 202216 Feb 202749.5 MW
Port Ham 132Kv S Stn (solar)7 Apr 202230 Dec 202799 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2026: 144 MW2027: 673 MW20262027673 MW
0 MW400 MW800 MW2026: 144 MW2027: 673 MW20262027673 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026144.4 MW
2027672.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Port Ham 132Kv S Stn (solar)45 MW0 MW13 Oct 2026not statedgate not printedAccepted to Connect
2Port Ham 132Kv S Stn (solar)49.9 MW45 MW1 Dec 2026not statedgate not printedAccepted to Connect
3Port Ham 132Kv S Stn (solar)49.5 MW94.9 MW23 Dec 2026not statedgate not printedAccepted to Connect
4Port Ham 132Kv S Stn (solar)60 MW144.4 MW7 Jan 2027not statedgate not printedAccepted to Connect
5Port Ham 132Kv S Stn (solar)40 MW204.4 MW21 Jan 2027not statedgate not printedAccepted to Connect
6Port Ham 132Kv S Stn (bess)99.9 MW244.4 MW26 Jan 2027not statedgate not printedAccepted to Connect
7Port Ham 132Kv S Stn (bess)49.9 MW344.3 MW28 Jan 2027not statedgate not printedAccepted to Connect
8Port Ham 132Kv S Stn (bess)49.9 MW394.2 MW11 Feb 2027not statedgate not printedAccepted to Connect
9Port Ham 132Kv S Stn (bess)40 MW444.1 MW11 Feb 2027not statedgate not printedAccepted to Connect
10Port Ham 132Kv S Stn (solar)40 MW484.1 MW12 Feb 2027not statedgate not printedAccepted to Connect
11Port Ham 132Kv S Stn (solar)49.5 MW524.1 MW16 Feb 2027not statedgate not printedAccepted to Connect
12Port Ham 132Kv S Stn (solar)99 MW573.6 MW30 Dec 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20263144.4 MW
20279528.2 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Port Ham 132Kv S Stn (battery, 99.9 MW)Battery storage99.9 MW26 Jan 2027Accepted to Connect
Port Ham 132Kv S Stn (solar, 99 MW)Solar99 MW30 Dec 2027Accepted to Connect
Port Ham 132Kv S Stn (battery, 49.9 MW)Battery storage49.9 MW28 Jan 2027Accepted to Connect
Port Ham 132Kv S Stn (battery, 49.9 MW)Battery storage49.9 MW11 Feb 2027Accepted to Connect
Port Ham 132Kv S Stn (solar, 49.9 MW)Solar49.9 MW1 Dec 2026Accepted to Connect
Port Ham 132Kv S Stn (solar, 49.5 MW)Solar49.5 MW16 Feb 2027Accepted to Connect
Port Ham 132Kv S Stn (solar, 49.5 MW)Solar49.5 MW23 Dec 2026Accepted to Connect
Port Ham 132Kv S Stn (solar, 47.41 MW)Solar47.41 MWnot statedConnected
Port Ham 132Kv S Stn (solar, 47.41 MW)Solar47.41 MWnot statedConnected
Port Ham 132Kv S Stn (solar, 45 MW)Solar45 MW13 Oct 2026Accepted to Connect
Port Ham 132Kv S Stn (solar, 40 MW)Solar40 MW12 Feb 2027Accepted to Connect
Port Ham 132Kv S Stn (solar, 40 MW)Solar40 MW21 Jan 2027Accepted to Connect
Port Ham 132Kv S Stn (solar, 40 MW)Solar40 MW7 Jan 2027Accepted to Connect
Port Ham 132Kv S Stn (battery, 40 MW)Battery storage40 MW11 Feb 2027Accepted to Connect
Port Ham 132Kv S Stn (solar, 23.75 MW)Solar23.75 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.