N84 Grid

Pyworthy Bsp

DNO substation.

Contracted here0.10 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date1 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue95.78 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Pyworthy Bsp (solar)25 Oct 20211 Dec 20265.59 MW
Pyworthy Bsp (solar)12 Sep 20253 Feb 202730 MW
Pyworthy Bsp (solar)30 Jan 202622 Apr 202725 MW
Pyworthy Bsp (solar)7 Jun 202329 Sep 20273.19 MW
Pyworthy Bsp (solar)13 Nov 202011 Nov 202732 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2026: 6 MW2027: 96 MW2026202796 MW
0 MW50 MW100 MW2026: 6 MW2027: 96 MW2026202796 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20265.59 MW
202795.78 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Pyworthy Bsp (solar)5.59 MW0 MW1 Dec 2026not statedgate not printedAccepted to Connect
2Pyworthy Bsp (solar)30 MW5.59 MW3 Feb 2027not statedgate not printedAccepted to Connect
3Pyworthy Bsp (solar)25 MW35.59 MW22 Apr 2027not statedgate not printedAccepted to Connect
4Pyworthy Bsp (solar)3.19 MW60.59 MW29 Sep 2027not statedgate not printedAccepted to Connect
5Pyworthy Bsp (solar)32 MW63.78 MW11 Nov 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202615.59 MW
2027490.19 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Pyworthy Bsp (solar, 61.18 MW)Solar61.18 MWnot statedConnected
Pyworthy Bsp (solar, 32 MW)Solar32 MW11 Nov 2027Accepted to Connect
Pyworthy Bsp (solar, 30 MW)Solar30 MW3 Feb 2027Accepted to Connect
Pyworthy Bsp (solar, 25 MW)Solar25 MW22 Apr 2027Accepted to Connect
Pyworthy Bsp (solar, 11.67 MW)Solar11.67 MWnot statedConnected
Pyworthy Bsp (solar, 9.04 MW)Solar9.04 MWnot statedConnected
Pyworthy Bsp (solar, 6.68 MW)Solar6.68 MWnot statedConnected
Pyworthy Bsp (onshore wind, 6.15 MW)Onshore wind6.15 MWnot statedConnected
Pyworthy Bsp (solar, 5.59 MW)Solar5.59 MW1 Dec 2026Accepted to Connect
Pyworthy Bsp (solar, 5 MW)Solar5 MWnot statedConnected
Pyworthy Bsp (solar, 4.75 MW)Solar4.75 MWnot statedConnected
Pyworthy Bsp (solar, 4.75 MW)Solar4.75 MWnot statedConnected
Pyworthy Bsp (solar, 4.75 MW)Solar4.75 MWnot statedConnected
Pyworthy Bsp (hybrid, 4.43 MW)Hybrid4.43 MWnot statedConnected
Pyworthy Bsp (onshore wind, 3.8 MW)Onshore wind3.8 MWnot statedConnected
Pyworthy Bsp (solar, 3.33 MW)Solar3.33 MWnot statedConnected
Pyworthy Bsp (solar, 3.19 MW)Solar3.19 MW29 Sep 2027Accepted to Connect
Pyworthy Bsp (solar, 3.13 MW)Solar3.14 MWnot statedConnected
Pyworthy Bsp (solar, 3.03 MW)Solar3.03 MWnot statedConnected
Pyworthy Bsp (other, 2.85 MW)Other2.85 MWnot statedConnected
Pyworthy Bsp (hybrid, 1.14 MW)Hybrid1.14 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.