N84 Grid

Redruth

DNO substation.

Contracted here0.00 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date27 Oct 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue2.9 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Redruth (solar)28 Jun 202427 Oct 20261.9 MW
Redruth (solar)19 Jun 202531 Dec 20260.95 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2 MW4 MW2026: 3 MW20263 MW
0 MW2 MW4 MW2026: 3 MW20263 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20262.85 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Redruth (solar)1.9 MW0 MW27 Oct 2026not statedgate not printedAccepted to Connect
2Redruth (solar)0.95 MW1.9 MW31 Dec 2026not statedgate not printedAccepted to Connect
3Redruth (solar)0.05 MW2.85 MWnot statednot statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202622.85 MW
not stated10.05 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Redruth (solar, 0.67 MW)Solar0.67 MW31 Dec 2026Accepted to Connect
Redruth (solar, 0.64 MW)Solar0.64 MW27 Oct 2026Accepted to Connect
Redruth (solar, 0.38 MW)Solar0.38 MWnot statedConnected
Redruth (solar, 0.17 MW)Solar0.17 MWnot statedConnected
Redruth (solar, 0.17 MW)Solar0.17 MWnot statedConnected
Redruth (solar, 0.11 MW)Solar0.11 MWnot statedConnected
Redruth (solar, 0.1 MW)Solar0.1 MWnot statedConnected
Redruth (solar, 0.1 MW)Solar0.1 MWnot statedConnected
Redruth (solar, 0.09 MW)Solar0.09 MWnot statedConnected
Redruth (solar, 0.07 MW)Solar0.07 MWnot statedConnected
Redruth (solar, 0.05 MW)Solar0.05 MWnot statedConnected
Redruth (solar, 0.05 MW)Solar0.05 MWnot statedAccepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.