Rhos Primary

DNO substation.

Contracted here0.11 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date1 Sep 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue109.94 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Rhos Primary (wind on)19 Feb 20251 Sep 20260.9 MW
Rhos Primary (hybrid)4 Jun 202515 Dec 20260.09 MW
Rhos Grid (hybrid)22 Dec 20255 Oct 2037108.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 1 MW2037: 110 MW202620282030203220342037110 MW
0 MW100 MW200 MW2026: 1 MW2037: 110 MW20262029203220352037110 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20260.99 MW
2037109.89 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Rhos Primary (wind on)0.9 MW0 MW1 Sep 2026not statedgate not printedAccepted to Connect
2Rhos Primary (hybrid)0.09 MW0.9 MW15 Dec 2026not statedgate not printedAccepted to Connect
3Rhos Grid (hybrid)108.9 MW0.99 MW5 Oct 2037not statedgate not printedAccepted to Connect
4Rhos Primary (solar)0.05 MW109.89 MWnot statednot statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202620.99 MW
20371108.9 MW
not stated10.05 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Rhos Primary (hybrid, 58.5 MW)Hybrid58.5 MW5 Oct 2037Accepted to Connect
Rhos Primary (onshore wind, 21.85 MW)Onshore wind21.85 MWnot statedConnected
Rhos Primary (solar, 6.21 MW)Solar6.21 MWnot statedConnected
Rhos Primary (solar, 5.7 MW)Solar5.7 MWnot statedConnected
Rhos Primary (onshore wind, 4.66 MW)Onshore wind4.66 MWnot statedConnected
Rhos Primary (onshore wind, 0.9 MW)Onshore wind0.9 MW1 Sep 2026Accepted to Connect
Rhos Primary (onshore wind, 0.5 MW)Onshore wind0.5 MWnot statedConnected
Rhos Primary (onshore wind, 0.22 MW)Onshore wind0.22 MWnot statedConnected
Rhos Primary (onshore wind, 0.17 MW)Onshore wind0.17 MWnot statedConnected
Rhos Primary (solar, 0.09 MW)Solar0.09 MWnot statedConnected
Rhos Primary (onshore wind, 0.09 MW)Onshore wind0.09 MWnot statedConnected
Rhos Primary (onshore wind, 0.09 MW)Onshore wind0.09 MWnot statedConnected
Rhos Primary (onshore wind, 0.09 MW)Onshore wind0.09 MWnot statedConnected
Rhos Primary (onshore wind, 0.09 MW)Onshore wind0.09 MWnot statedConnected
Rhos Primary (hybrid, 0.09 MW)Hybrid0.09 MW15 Dec 2026Accepted to Connect
Rhos Primary (solar, 0.07 MW)Solar0.07 MWnot statedConnected
Rhos Primary (onshore wind, 0.06 MW)Onshore wind0.06 MWnot statedConnected
Rhos Primary (solar, 0.05 MW)Solar0.05 MWnot statedAccepted to Connect
Rhos Primary (solar, 0.04 MW)Solar0.04 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.