Seabank Sgp

DNO substation.

Contracted here0.16 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date20 May 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue160 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Seabank Sgp (gas)3 Apr 201720 May 202720 MW
Seabank Sgp (bess)12 May 202210 Sep 202770 MW
Seabank Sgp (bess)26 Jul 202318 Dec 203770 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 90 MW2037: 160 MW202720292031203320352037160 MW
0 MW100 MW200 MW2027: 90 MW2037: 160 MW2027203020332037160 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202790 MW
2037160 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Seabank Sgp (gas)20 MW0 MW20 May 2027not statedgate not printedAccepted to Connect
2Seabank Sgp (bess)70 MW20 MW10 Sep 2027not statedgate not printedAccepted to Connect
3Seabank Sgp (bess)70 MW90 MW18 Dec 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027290 MW
2037170 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Seabank Sgp (battery, 70 MW)Battery storage70 MW18 Dec 2037Accepted to Connect
Seabank Sgp (battery, 70 MW)Battery storage70 MW10 Sep 2027Accepted to Connect
Seabank Sgp (thermal, 38 MW)Thermal38 MWnot statedConnected
Seabank Sgp (gas, 20 MW)Gas20 MW20 May 2027Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.