N84 Grid

Shrewsbury 132/33Kv

DNO substation.

Contracted here0.32 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date17 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue324.9 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Shrewsbury 132/33Kv (bess)16 Jan 202517 Dec 202635 MW
Shrewsbury 132/33Kv (hybrid)4 Jun 202514 Jan 2027240 MW
Shrewsbury 132/33Kv (solar)22 Apr 202626 Jun 202849.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2026: 35 MW2027: 275 MW2028: 325 MW202620272028325 MW
0 MW200 MW400 MW2026: 35 MW2027: 275 MW2028: 325 MW202620272028325 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202635 MW
2027275 MW
2028324.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Shrewsbury 132/33Kv (bess)35 MW0 MW17 Dec 2026not statedgate not printedAccepted to Connect
2Shrewsbury 132/33Kv (hybrid)240 MW35 MW14 Jan 2027not statedgate not printedAccepted to Connect
3Shrewsbury 132/33Kv (solar)49.9 MW275 MW26 Jun 2028not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026135 MW
20271240 MW
2028149.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Shrewsbury 132/33Kv (hybrid, 80 MW)Hybrid80 MW14 Jan 2027Accepted to Connect
Shrewsbury 132/33Kv (solar, 49.9 MW)Solar49.9 MW26 Jun 2028Accepted to Connect
Shrewsbury 132/33Kv (battery, 35 MW)Battery storage35 MW17 Dec 2026Accepted to Connect
Shrewsbury 132/33Kv (solar, 16.15 MW)Solar16.15 MWnot statedConnected
Shrewsbury 132/33Kv (solar, 14.25 MW)Solar14.25 MWnot statedConnected
Shrewsbury 132/33Kv (solar, 9.5 MW)Solar9.5 MWnot statedConnected
Shrewsbury 132/33Kv (thermal, 9.21 MW)Thermal9.22 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.