N84 Grid

Shrewsbury 132Kv S Stn

DNO substation.

Contracted here0.10 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date3 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue95.63 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Shrewsbury 132Kv S Stn (bess)19 Mar 20253 Dec 202617 MW
Shrewsbury 132Kv S Stn (solar)7 Apr 202121 Jan 202721 MW
Shrewsbury 132Kv S Stn (solar)29 Dec 202028 Jan 202725 MW
Shrewsbury 132Kv S Stn (bess)16 Aug 202112 Feb 202710.63 MW
Shrewsbury 132Kv S Stn (solar)8 Oct 20211 Oct 202812 MW
Shrewsbury 132Kv S Stn (bess)20 Mar 202522 May 203710 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2026: 17 MW2027: 74 MW2028: 86 MW2037: 96 MW20262028203020322034203796 MW
0 MW50 MW100 MW2026: 17 MW2027: 74 MW2028: 86 MW2037: 96 MW2026202920322035203796 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202617 MW
202773.63 MW
202885.63 MW
203795.63 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Shrewsbury 132Kv S Stn (bess)17 MW0 MW3 Dec 2026not statedgate not printedAccepted to Connect
2Shrewsbury 132Kv S Stn (solar)21 MW17 MW21 Jan 2027not statedgate not printedAccepted to Connect
3Shrewsbury 132Kv S Stn (solar)25 MW38 MW28 Jan 2027not statedgate not printedAccepted to Connect
4Shrewsbury 132Kv S Stn (bess)10.63 MW63 MW12 Feb 2027not statedgate not printedAccepted to Connect
5Shrewsbury 132Kv S Stn (solar)12 MW73.63 MW1 Oct 2028not statedgate not printedAccepted to Connect
6Shrewsbury 132Kv S Stn (bess)10 MW85.63 MW22 May 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026117 MW
2027356.63 MW
2028112 MW
2037110 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Shrewsbury 132Kv S Stn (solar, 25 MW)Solar25 MW28 Jan 2027Accepted to Connect
Shrewsbury 132Kv S Stn (solar, 21 MW)Solar21 MW21 Jan 2027Accepted to Connect
Shrewsbury 132Kv S Stn (battery, 17 MW)Battery storage17 MW3 Dec 2026Accepted to Connect
Shrewsbury 132Kv S Stn (solar, 12 MW)Solar12 MW1 Oct 2028Accepted to Connect
Shrewsbury 132Kv S Stn (battery, 10.63 MW)Battery storage10.63 MW12 Feb 2027Accepted to Connect
Shrewsbury 132Kv S Stn (battery, 10 MW)Battery storage10 MW22 May 2037Accepted to Connect

Supported by NGED Open Data