Skegness 33Kv S Stn

DNO substation.

Contracted here0.05 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue50 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Skegness 33Kv S Stn (hybrid)18 Apr 202331 Dec 202640 MW
Skegness 33Kv S Stn (solar)6 Jan 202523 Mar 202710 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW25 MW50 MW2026: 40 MW2027: 50 MW2026202750 MW
0 MW25 MW50 MW2026: 40 MW2027: 50 MW2026202750 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202640 MW
202750 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Skegness 33Kv S Stn (hybrid)40 MW0 MW31 Dec 2026not statedgate not printedAccepted to Connect
2Skegness 33Kv S Stn (solar)10 MW40 MW23 Mar 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026140 MW
2027110 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Skegness 33Kv S Stn (hybrid, 30 MW)Hybrid30 MW31 Dec 2026Accepted to Connect
Skegness 33Kv S Stn (solar, 17.86 MW)Solar17.86 MWnot statedConnected
Skegness 33Kv S Stn (solar, 9.6 MW)Solar9.6 MW23 Mar 2027Accepted to Connect
Skegness 33Kv S Stn (solar, 9.5 MW)Solar9.5 MWnot statedConnected
Skegness 33Kv S Stn (onshore wind, 9.12 MW)Onshore wind9.12 MWnot statedConnected
Skegness 33Kv S Stn (solar, 8.36 MW)Solar8.36 MWnot statedConnected
Skegness 33Kv S Stn (onshore wind, 2.66 MW)Onshore wind2.66 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.