N84 Grid

Staveley 33Kv S Stn

DNO substation.

Contracted here0.04 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date15 May 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue36 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Staveley 33Kv S Stn (bess)2 Apr 201915 May 20266 MW
Staveley 33Kv S Stn (hybrid)28 Jun 202126 Feb 202730 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW20 MW40 MW2026: 6 MW2027: 36 MW2026202736 MW
0 MW20 MW40 MW2026: 6 MW2027: 36 MW2026202736 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20266 MW
202736 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Staveley 33Kv S Stn (bess)6 MW0 MW15 May 2026not statedgate not printedAccepted to Connect
2Staveley 33Kv S Stn (hybrid)30 MW6 MW26 Feb 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202616 MW
2027130 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Staveley 33Kv S Stn (solar, 19 MW)Solar19 MWnot statedConnected
Staveley 33Kv S Stn (hybrid, 10 MW)Hybrid10 MW26 Feb 2027Accepted to Connect
Staveley 33Kv S Stn (gas, 6.65 MW)Gas6.65 MWnot statedConnected
Staveley 33Kv S Stn (battery, 6 MW)Battery storage6 MW15 May 2026Accepted to Connect
Staveley 33Kv S Stn (solar, 3.99 MW)Solar3.99 MWnot statedConnected
Staveley 33Kv S Stn (gas, 2.8 MW)Gas2.8 MWnot statedConnected
Staveley 33Kv S Stn (solar, 0.43 MW)Solar0.43 MWnot statedConnected