N84 Grid

Stourport 132 66 33Kv S Stn

DNO substation.

Contracted here0.08 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date22 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue80 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Stourport 132 66 33Kv S Stn (solar)26 Nov 202022 Dec 202625 MW
Stourport 132 66 33Kv S Stn (solar)4 Oct 202122 Dec 202630 MW
Stourport 132 66 33Kv S Stn (solar)10 Nov 20214 Jan 202725 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW40 MW80 MW2026: 55 MW2027: 80 MW2026202780 MW
0 MW40 MW80 MW2026: 55 MW2027: 80 MW2026202780 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202655 MW
202780 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Stourport 132 66 33Kv S Stn (solar)25 MW0 MW22 Dec 2026not statedgate not printedAccepted to Connect
2Stourport 132 66 33Kv S Stn (solar)30 MW25 MW22 Dec 2026not statedgate not printedAccepted to Connect
3Stourport 132 66 33Kv S Stn (solar)25 MW55 MW4 Jan 2027not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026255 MW
2027125 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Stourport 132 66 33Kv S Stn (solar, 30 MW)Solar30 MW22 Dec 2026Accepted to Connect
Stourport 132 66 33Kv S Stn (solar, 25 MW)Solar25 MW22 Dec 2026Accepted to Connect
Stourport 132 66 33Kv S Stn (solar, 25 MW)Solar25 MW4 Jan 2027Accepted to Connect
Stourport 132 66 33Kv S Stn (solar, 4.23 MW)Solar4.23 MWnot statedConnected

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.