N84 Grid

Swansea North Bsp

DNO substation.

Contracted here0.25 GWNot yet connected, as printed
Entries in the queue9entries with a printed MW
Earliest connection date30 Nov 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue166.58 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Swansea North Bsp (solar)3 Jun 202430 Nov 20260.44 MW
Swansea North Grid (wind on)14 Jul 201530 Dec 202620 MW
Swansea North Bsp (solar)6 Sep 20195 Apr 202730 MW
Swansea North Grid (solar)5 Jan 202319 May 202712.69 MW
Swansea North Bsp (solar)8 Jul 20206 Jul 202715.45 MW
Swansea North Grid (hybrid)30 Dec 202430 Sep 202788 MW
Swansea North Bsp (gas)17 Nov 202130 Oct 202720 MW
Swansea North Bsp (solar)9 Jun 202531 Dec 202715 MW
Swansea North Bsp (wind on)1 Mar 202330 Jun 202949 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2026: 20 MW2027: 202 MW2029: 251 MW2026202720282029251 MW
0 MW200 MW400 MW2026: 20 MW2027: 202 MW2029: 251 MW2026202720282029251 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202620.44 MW
2027201.58 MW
2029250.58 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Swansea North Bsp (solar)0.44 MW0 MW30 Nov 2026not statedgate not printedAccepted to Connect
2Swansea North Grid (wind on)20 MW0.44 MW30 Dec 2026not statedgate not printedAccepted to Connect
3Swansea North Bsp (solar)30 MW20.44 MW5 Apr 2027not statedgate not printedAccepted to Connect
4Swansea North Grid (solar)12.69 MW50.44 MW19 May 2027not statedgate not printedAccepted to Connect
5Swansea North Bsp (solar)15.45 MW63.13 MW6 Jul 2027not statedgate not printedAccepted to Connect
6Swansea North Grid (hybrid)88 MW78.58 MW30 Sep 2027not statedgate not printedAccepted to Connect
7Swansea North Bsp (gas)20 MW166.58 MW30 Oct 2027not statedgate not printedAccepted to Connect
8Swansea North Bsp (solar)15 MW186.58 MW31 Dec 2027not statedgate not printedAccepted to Connect
9Swansea North Bsp (wind on)49 MW201.58 MW30 Jun 2029not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the NGED Embedded Capacity Register, file dated 14 Aug 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026220.44 MW
20276181.14 MW
2029149 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Swansea North Bsp (onshore wind, 57.48 MW)Onshore wind57.48 MWnot statedConnected
Swansea North Bsp (onshore wind, 49 MW)Onshore wind49 MW30 Jun 2029Accepted to Connect
Swansea North Bsp (hybrid, 44.9 MW)Hybrid44.9 MW30 Sep 2027Accepted to Connect
Swansea North Bsp (onshore wind, 35.15 MW)Onshore wind35.15 MWnot statedConnected
Swansea North Bsp (onshore wind, 31.16 MW)Onshore wind31.16 MWnot statedConnected
Swansea North Bsp (solar, 30 MW)Solar30 MW5 Apr 2027Accepted to Connect
Swansea North Bsp (onshore wind, 24.7 MW)Onshore wind24.7 MWnot statedConnected
Swansea North Bsp (gas, 20 MW)Gas20 MW30 Oct 2027Accepted to Connect
Swansea North Bsp (onshore wind, 20 MW)Onshore wind20 MW30 Dec 2026Accepted to Connect
Swansea North Bsp (gas, 19 MW)Gas19 MWnot statedConnected
Swansea North Bsp (solar, 15.45 MW)Solar15.45 MW6 Jul 2027Accepted to Connect
Swansea North Bsp (solar, 15 MW)Solar15 MW31 Dec 2027Accepted to Connect
Swansea North Bsp (solar, 12.69 MW)Solar12.69 MW19 May 2027Accepted to Connect
Swansea North Bsp (solar, 8.55 MW)Solar8.55 MWnot statedConnected
Swansea North Bsp (solar, 8.55 MW)Solar8.55 MWnot statedConnected
Swansea North Bsp (solar, 6.4 MW)Solar6.4 MWnot statedConnected
Swansea North Bsp (solar, 5.7 MW)Solar5.7 MWnot statedConnected
Swansea North Bsp (solar, 4.75 MW)Solar4.75 MWnot statedConnected
Swansea North Bsp (solar, 4.08 MW)Solar4.08 MWnot statedConnected
Swansea North Bsp (solar)Solar0 MW30 Nov 2026Accepted to Connect

Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.